QUESTION 1
According to OSHA 1926.1408, what is the minimum clearance distance
required for power lines rated up to 50 kV when the crane is in
operation?
• A. 5 feet
• B. 10 feet
• C. 15 feet
• D. 20 feet
Correct Answer: B. 10 feet
Detailed Rationale: For lines rated 50 kV or below, OSHA mandates a
minimum clearance of 10 feet between any part of the crane/load and
the power line, unless the voltage is higher or utility owner confirms
lines are de-energized and grounded.
QUESTION 2
When setting up a mobile crane on outriggers, what is the standard
requirement regarding outrigger deployment unless the manufacturer’s
load chart specifies otherwise?
• A. Outriggers must be extended halfway with tires touching the
ground.
, • B. Outriggers must be fully extended and properly pinned or
locked, with tires raised off the ground.
• C. Outriggers are optional if the crane is under 50 tons capacity.
• D. Outriggers only need to be deployed on the side carrying the
load.
Correct Answer: B. Outriggers must be fully extended and properly
pinned or locked, with tires raised off the ground.
Detailed Rationale: Standard crane operations on outriggers require
them to be fully extended (and outrigger pads properly
blocked/cribbed) with the tires completely clear of the supporting
surface, as rated capacities assume this configuration.
QUESTION 3
What is the definition of "Net Capacity" on a crane load chart?
• A. The total weight of the crane including counterweights and
boom.
• B. The maximum lifting capacity of the crane minus structural
safety factors.
• C. The gross capacity of the crane minus the weight of all lifting
attachments, such as the hook block, rigging, and auxiliary drop
ball.
• D. The weight of the load only, excluding rigging hardware.
Correct Answer: C. The gross capacity of the crane minus the weight of
all lifting attachments, such as the hook block, rigging, and auxiliary
drop ball.
,Detailed Rationale: Net capacity (or allowable load) is what is actually
available to lift. To find it, you must subtract all load-handling devices
(block, ball, slings, shackles) from the chart's gross capacity.
QUESTION 4
According to standard hand signals (ASME B30.5), what does extending
both arms with palms down and moving them horizontally back and
forth indicate?
• A. Raise Boom
• B. Lower Boom
• C. Emergency Stop
• D. Stop
Correct Answer: D. Stop
Detailed Rationale: Extending both arms out horizontally with palms
down and moving them back and forth is the universal signal for a
standard "Stop."
QUESTION 5
When lifting a load, where must the crane's hook be positioned relative
to the load's center of gravity to prevent swinging or tipping?
• A. Directly above the center of gravity.
• B. As close to the edge of the load as possible.
• C. Offset toward the longest side of the load.
• D. Positioned randomly as long as the rigging holds.
Correct Answer: A. Directly above the center of gravity.
, Detailed Rationale: The crane hook must always be centered directly
above the load's center of gravity prior to lifting to prevent the load
from shifting, swinging, or side-loading the boom.
QUESTION 6
What happens to the load radius when a crane's boom is deflected
downward under a heavy load?
• A. The load radius decreases.
• B. The load radius increases.
• C. The load radius remains completely unchanged.
• D. The boom angle automatically increases.
Correct Answer: B. The load radius increases.
Detailed Rationale: Under heavy loads, boom deflection causes the tip
of the boom to move outward (away from the crane), increasing the
load radius, which can adversely affect stability and capacity.
QUESTION 7
What is "Two-Blocking"?
• A. Using two crane blocks simultaneously for a tandem lift.
• B. A condition where the lower load block or hook ball comes into
physical contact with the upper boom tip / sheave assembly.
• C. Locking two outrigger beams together for stability.
• D. Spooling two wire ropes onto a single winch drum.
Correct Answer: B. A condition where the lower load block or hook ball
comes into physical contact with the upper boom tip / sheave assembly.
Practice Questions, Verified Answers & Detailed Rationales
(2026/2027)
QUESTION 1
According to OSHA 1926.1408, what is the minimum clearance distance
required for power lines rated up to 50 kV when the crane is in
operation?
• A. 5 feet
• B. 10 feet
• C. 15 feet
• D. 20 feet
Correct Answer: B. 10 feet
Detailed Rationale: For lines rated 50 kV or below, OSHA mandates a
minimum clearance of 10 feet between any part of the crane/load and
the power line, unless the voltage is higher or utility owner confirms
lines are de-energized and grounded.
QUESTION 2
When setting up a mobile crane on outriggers, what is the standard
requirement regarding outrigger deployment unless the manufacturer’s
load chart specifies otherwise?
• A. Outriggers must be extended halfway with tires touching the
ground.
, • B. Outriggers must be fully extended and properly pinned or
locked, with tires raised off the ground.
• C. Outriggers are optional if the crane is under 50 tons capacity.
• D. Outriggers only need to be deployed on the side carrying the
load.
Correct Answer: B. Outriggers must be fully extended and properly
pinned or locked, with tires raised off the ground.
Detailed Rationale: Standard crane operations on outriggers require
them to be fully extended (and outrigger pads properly
blocked/cribbed) with the tires completely clear of the supporting
surface, as rated capacities assume this configuration.
QUESTION 3
What is the definition of "Net Capacity" on a crane load chart?
• A. The total weight of the crane including counterweights and
boom.
• B. The maximum lifting capacity of the crane minus structural
safety factors.
• C. The gross capacity of the crane minus the weight of all lifting
attachments, such as the hook block, rigging, and auxiliary drop
ball.
• D. The weight of the load only, excluding rigging hardware.
Correct Answer: C. The gross capacity of the crane minus the weight of
all lifting attachments, such as the hook block, rigging, and auxiliary
drop ball.
,Detailed Rationale: Net capacity (or allowable load) is what is actually
available to lift. To find it, you must subtract all load-handling devices
(block, ball, slings, shackles) from the chart's gross capacity.
QUESTION 4
According to standard hand signals (ASME B30.5), what does extending
both arms with palms down and moving them horizontally back and
forth indicate?
• A. Raise Boom
• B. Lower Boom
• C. Emergency Stop
• D. Stop
Correct Answer: D. Stop
Detailed Rationale: Extending both arms out horizontally with palms
down and moving them back and forth is the universal signal for a
standard "Stop."
QUESTION 5
When lifting a load, where must the crane's hook be positioned relative
to the load's center of gravity to prevent swinging or tipping?
• A. Directly above the center of gravity.
• B. As close to the edge of the load as possible.
• C. Offset toward the longest side of the load.
• D. Positioned randomly as long as the rigging holds.
Correct Answer: A. Directly above the center of gravity.
, Detailed Rationale: The crane hook must always be centered directly
above the load's center of gravity prior to lifting to prevent the load
from shifting, swinging, or side-loading the boom.
QUESTION 6
What happens to the load radius when a crane's boom is deflected
downward under a heavy load?
• A. The load radius decreases.
• B. The load radius increases.
• C. The load radius remains completely unchanged.
• D. The boom angle automatically increases.
Correct Answer: B. The load radius increases.
Detailed Rationale: Under heavy loads, boom deflection causes the tip
of the boom to move outward (away from the crane), increasing the
load radius, which can adversely affect stability and capacity.
QUESTION 7
What is "Two-Blocking"?
• A. Using two crane blocks simultaneously for a tandem lift.
• B. A condition where the lower load block or hook ball comes into
physical contact with the upper boom tip / sheave assembly.
• C. Locking two outrigger beams together for stability.
• D. Spooling two wire ropes onto a single winch drum.
Correct Answer: B. A condition where the lower load block or hook ball
comes into physical contact with the upper boom tip / sheave assembly.