Written by students who passed Immediately available after payment Read online or as PDF Wrong document? Swap it for free 4.6 TrustPilot
logo-home
Document preview thumbnail
Preview 4 out of 61 pages
Exam (elaborations)

[WGU-D199 EXAM] – EXAM-STYLE QUESTIONS AND ANSWERS | VERIFIED AND WELL DETAILED ANSWERS | PLUS RATIONALES | GUARANTEED PASS | 2026/27 LATEST UPDATE | EXAM PREP | STUDY GUIDE | PRACTICE TEST

Document preview thumbnail
Preview 4 out of 61 pages

[WGU-D199 EXAM] – EXAM-STYLE QUESTIONS AND ANSWERS | VERIFIED AND WELL DETAILED ANSWERS | PLUS RATIONALES | GUARANTEED PASS | 2026/27 LATEST UPDATE | EXAM PREP | STUDY GUIDE | PRACTICE TEST

Content preview

[WGU-D199 EXAM] – EXAM-STYLE QUESTIONS AND ANSWERS | VERIFIED AND
WELL DETAILED ANSWERS | PLUS RATIONALES | GUARANTEED PASS | 2026/27
LATEST UPDATE | EXAM PREP | STUDY GUIDE | PRACTICE TEST

SECTION ONE: QUESTIONS 1-50

1. A company's accounting department is migrating from a legacy on-premises
ERP system to a cloud-based solution. The project manager is tasked with
ensuring that the migration does not disrupt financial reporting for the current
fiscal quarter. What is the project manager's PRIMARY responsibility during the
initiation phase of this project?

A. Drafting a detailed project schedule with specific tasks for data validation.
B. Defining the project scope and securing formal approval from key
stakeholders.
C. Assigning technical roles to IT staff members for the data migration process.
D. Procuring the new cloud-based software licenses for the accounting
department.

Correct Answer: B. Defining the project scope and securing formal approval
from key stakeholders.

Rationale: During the initiation phase, the primary responsibility of a project
manager is to define the high-level scope, objectives, and deliverables, and to
obtain formal authorization from the project sponsor and key stakeholders. This
provides the foundation for all subsequent planning. Options A, C, and D are
activities that occur during the planning and execution phases, not the initiation
phase.

,2. An IT director is evaluating business cases for several potential projects. One
project involves upgrading the network infrastructure, while another focuses
on implementing a new customer relationship management (CRM) system.
Which criterion is MOST critical for determining which project should receive
funding first?

A. The project with the highest net present value (NPV).
B. The project that can be completed with the smallest budget.
C. The project that aligns most closely with the organization's strategic goals.
D. The project that requires the fewest internal resources to implement.

Correct Answer: C. The project that aligns most closely with the organization's
strategic goals.

Rationale: While financial metrics like NPV (A), cost (B), and resource requirements
(D) are important, the primary driver for project selection should be strategic
alignment. A project may have a lower NPV but be critical for entering a new
market or meeting a regulatory requirement, making it more valuable to the
organization's long-term success.

3. A project team is in the middle of a complex software development project.
The team has consistently missed sprint deadlines, and the product owner is
becoming concerned about the final delivery date. What is the MOST effective
first step for the project manager to resolve this issue?

A. Reassign the development team members to different tasks.
B. Extend the project timeline to accommodate the delays.
C. Increase the amount of overtime required for the team.
D. Perform a root cause analysis to understand the reasons for the missed
deadlines.

,Correct Answer: D. Perform a root cause analysis to understand the reasons for
the missed deadlines.

Rationale: Before taking corrective action, it is essential to understand why the
deadlines are being missed. A root cause analysis (D) will identify the underlying
problems, such as unclear requirements, technical debt, or resource constraints. This
allows the project manager to implement a targeted and effective solution. Options
A, B, and C are reactive measures that do not address the core issue and may be
ineffective or detrimental.

4. A project sponsor requests a change to the project scope that will add a
significant new feature. The project manager has assessed the impact and
determined it will require additional budget and a timeline extension.
According to best practices, what should the project manager do NEXT?

A. Immediately begin work on the new feature to satisfy the sponsor.
B. Reject the change request to protect the project's original scope.
C. Submit a formal change request to the change control board (CCB) for review.
D. Negotiate with the sponsor to reduce other features to compensate for the
new one.

Correct Answer: C. Submit a formal change request to the change control
board (CCB) for review.

Rationale: A formal change management process is necessary for any change that
impacts the project baseline (scope, schedule, or budget). The project manager's role
is to document the impact and submit the request to the Change Control Board (C)
for a decision. This ensures all impacts are considered and approved before the
change is implemented. Options A and B bypass the governance process, while D
may be a solution after the CCB's review, not the next step.

, 5. A project manager is calculating the estimate at completion (EAC) for a
project. The project has a budget at completion (BAC) of $200,000. The actual
cost (AC) to date is $50,000, and the earned value (EV) is $45,000. The project
manager believes the current cost performance will continue for the remainder
of the project. What is the EAC?

A. $200,000
B. $222,222
C. $205,000
D. $195,000

Correct Answer: B. $222,222

Rationale: When the current cost performance is expected to continue, the formula
for EAC is BAC / Cost Performance Index (CPI). First, calculate CPI = EV / AC =
$45,000 / $50,000 = 0.9. Then, EAC = BAC / CPI = $200,.9 = $222,222. This
forecast indicates the project is over budget and will likely require more than the
original BAC if performance does not improve. The other options use incorrect
formulas or assumptions.

6. A project is in the execution phase, and the project manager notices that a
critical resource is being pulled in multiple directions, causing delays. The
project manager has a frank discussion with the resource's functional manager.
This scenario BEST describes which type of organizational structure?

A. Projectized
B. Strong Matrix
C. Weak Matrix
D. Functional

Document information

Uploaded on
August 6, 2026
Number of pages
61
Written in
2026/2027
Type
Exam (elaborations)
Contains
Questions & answers
$22.49

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
PrepPulse1
4.0
(21)
Sold
280
Followers
6
Items
3688
Last sold
1 day ago


Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions