Written by students who passed Immediately available after payment Read online or as PDF Wrong document? Swap it for free 4.6 TrustPilot
logo-home
Document preview thumbnail
Preview 4 out of 45 pages
Exam (elaborations)

CAPM Certified Associate in Project Management Practice Exam | Complete QUESTIONs, Verified Answers & Detailed Rationales (2026/2027)

Document preview thumbnail
Preview 4 out of 45 pages

CAPM Certified Associate in Project Management Practice Exam | Complete QUESTIONs, Verified Answers & Detailed Rationales (2026/2027)

Content preview

CAPM Certified Associate in Project Management Practice Exam |
Complete QUESTIONs, Verified Answers & Detailed Rationales
(2026/2027)


QUESTION 1
Which of the following characteristics best distinguishes a project from
ongoing operational work?
• A. Projects are repetitive, continuous, and have no predefined
completion date.
• B. Projects are temporary endeavors undertaken to create a
unique product, service, or result.
• C. Operations focus on delivering temporary business value while
projects focus on routine manufacturing.
• D. Projects rely entirely on standard, unchanging operational
procedures.
Correct Answer: B. Projects are temporary endeavors undertaken to
create a unique product, service, or result.
Detailed Rationale: By definition, a project has a definite beginning and
a distinct end (temporary) and produces a unique deliverable, whereas
operations are ongoing and repetitive.
QUESTION 2
According to the PMBOK Guide (7th Edition), which of the following is
one of the eight Project Performance Domains?
• A. Procurement Process Group

, • B. Stakeholder Performance Domain
• C. Cost-Benefit Matrix Domain
• D. Linear Scheduling Domain
Correct Answer: B. Stakeholder Performance Domain
Detailed Rationale: The PMBOK Guide 7th Edition organizes project
management around eight performance domains, which include
Stakeholders, Team, Development Approach and Life Cycle, Planning,
Project Work, Delivery, Measurement, and Uncertainty.
QUESTION 3
Who formally authorizes a project and gives the project manager the
authority to apply organizational resources to project activities?
• A. The Project Manager
• B. The Lead Technical Developer
• C. The Project Sponsor
• D. The Quality Assurance Auditor
Correct Answer: C. The Project Sponsor
Detailed Rationale: The project sponsor or initiator provides the
financial backing and issues the project charter, which formally
authorizes the project's existence and empowers the project manager.
QUESTION 4
What is the lowest, most granular level of decomposition within a Work
Breakdown Structure (WBS)?
• A. Project Milestone

, • B. Work Package
• C. Control Account
• D. Activity List
Correct Answer: B. Work Package
Detailed Rationale: The WBS decomposes project scope hierarchically.
The lowest level of breakdown for which cost and duration can be
estimated and managed is called a work package.
QUESTION 5
In network diagram analysis, what does "Total Float" (or slack)
represent?
• A. The total budget allocated for unforeseen risk reserves.
• B. The amount of time a schedule activity can be delayed from its
early start date without delaying the project end date.
• C. The total number of resources assigned to a critical task.
• D. The time required to complete administrative closure.
Correct Answer: B. The amount of time a schedule activity can be
delayed from its early start date without delaying the project end date.
Detailed Rationale: Total float measures schedule flexibility. Activities
with zero total float lie on the critical path, meaning any delay directly
pushes out the final project completion date.
QUESTION 6

, If a project has an Earned Value (EV) of $450,000 and an Actual Cost
(AC) of $500,000, what is the Cost Variance (CV) and what does it
indicate?
• A. CV = -$50,000; the project is over budget.
• B. CV = +$50,000; the project is under budget.
• C. CV = -$50,000; the project is ahead of schedule.
• D. CV = $0; the project is perfectly aligned with baseline costs.
Correct Answer: A. CV = -$50,000; the project is over budget.
Detailed Rationale: Cost Variance is calculated as 𝐶𝑉 = 𝐸𝑉 − 𝐴𝐶. Here,
$450,000 − $500,000 = −$50,000. A negative cost variance indicates
that the project has spent more money than the value of the work
completed.
QUESTION 7
A project has an Earned Value (EV) of $200,000 and a Planned Value
(PV) of $250,000. What is the Schedule Performance Index (SPI)?
• A. 1.25
• B. 0.80
• C. 0.50
• D. 1.50
Correct Answer: B. 0.80
Detailed Rationale: Schedule Performance Index is calculated as 𝑆𝑃𝐼 =
𝐸𝑉/𝑃𝑉. Thus, $200,000/$250,000 = 0.80. An SPI less than 1.0

Document information

Uploaded on
August 3, 2026
Number of pages
45
Written in
2026/2027
Type
Exam (elaborations)
Contains
Questions & answers
$21.99

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
CreativeWrites
3.6
(21)
Sold
88
Followers
3
Items
7835
Last sold
3 days ago



Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions