WGU C783 Project Management Objective Assessment
– Latest Official Exam
Develop Project Charter Inputs .......Answer....... Business
documents, Agreements, Enterprise Enviro. factors, and Org.
process assets
Develop Project Charter Tools & Techniques x
.......Answer.........Expert judgement, data gathering, interpersonal
& team skills, and meetings. x
Develop Project Charter Outputs .......Answer. ..... Project
Charter, Assumption log
Develop PM Plan Inputs .......Answer.........Proj. charter, outputs
from other processes, Enterprise enviro. factors, and Org.
process assets
,age 2 of 100
Develop PM Plan Tool & Techniques .......Answer. ..... Expert
judgement, data gathering, interpersonal and team skills, and
meetings
Develop PM Plan Outputs .......Answer.........PM Plan
Direct and Manage Project Work, Inputs .......Answer. ..... PM
plan, proj. docs, approved change requests, enterprise enviro.
factors, and org. process assets
Direct and Manage Project Work, Tools & Techniques
.......Answer.........Expert judgement, PMIS, and meetings
Direct and Manage Project Work, Outputs
.......Answer.........Deliverables, work performance data, issue log,
change requests, PM plan updates, proj. docs. updates, and org.
process assets updates
,age 3 of 100
Manage Project Knowledge, Inputs .......Answer.........PM plan,
proj. docs., deliverables, enterprise enviro. factors, and org.
process assets
Manage Project Knowledge, Tools & Techniques
.......Answer.........Expert judgement, knowledge management,
information management, interpersonal & team skills
Manage Project Knowledge, Outputs .......Answer. Lessons
learned register, PM plan updates, and org. process assets
updates
Monitor and Control Project Work, Inputs .......Answer. ..... PM
plan, proj. docs, work performance information, agreements,
enter. enviro. factors, and org. process assets
, age 4 of 100
Monitor and Control Project Work, Tools and Techniques
.......Answer.........Expert judgement, data analysis, decision
making, and meetings
Monitor and Control Project Work, Outputs
.......Answer.........Work performance reports, change requests,
PM plan updates, and proj. docs updates
Perform Integrated Change Control, Inputs .......Answer. ..... PM
plan, proj. docs, work performance reports, change requests,
enter. enviro. factors, and org. process assets
Perform Integrated Change Control, Tools & Techniques
.......Answer.........Expert judgement, change control tools, data
analysis, decision making, and meetings