CMIT EXAM TEST BANK SOLVED QUESTIONS 100 PERCENT CORRECT ANSWERS
CMIT Exam Questions and Answers Verified
Solutions Latest Update 2026/2027
Question:
Construction management had its beginnings in the early to mid-1960's. Which of the following
factors contributed to the initial use of this delivery system? A) The need to reduce the overall time
and cost associated with project delivery. B) The increasing cost of money and the unpredictability
of project funding streams. C) The changing role of the general contractor and the increasing
numbers of specialty trade contractors. D) All of the above.
Answer:
D) All of the above.
Question:
The General Services Administration was the first federal agency to use construction management.
Answer:
True
Question:
The General Services Administration, the Department of Health, Education and Welfare (now
HHS), and the Veterans Administration ran into similar difficulties in the use of construction
management. Which of the following was/were common problems for all three agencies? A)
Funding restrictions B) Claims C) Change conditions D) All of the above
Answer:
D) All of the above
Question:
CMAA was formed and incorporated 1982 with its primary focus being the growth and
development of the construction management profession.
Answer:
,True
Question:
The CMAA Construction Management Standards of Practice is intended as a guide to the range of
services that constitute professional construction management. They seek to meet the documented
need for definitions of what construction management services are, without unduly structuring the
methodologies by which those services are provided by the CM.
Answer:
True
Question:
The goals of the Construction Management Association of America (CMAA) include: A) Setting
standards and developing contract documents for construction management practice. B) Expanding
the understanding of the construction management concept and its use in the marketplace. C)
Advocacy for construction management in the legislative, regulatory, and judicial arenas of federal,
state, and local governments. D) All of the above.
Answer:
D) All of the above
Question:
The fact that an individual is certified or licensed in any other profession does not, per se, establish
him/her as a qualified CM. True False
Answer:
True
Question:
Certification as a CM means the construction management practitioner has "state of the art"
knowledge and capability to practice construction management. True False
Answer:
False
,Question:
Recruiting and training are business matters and normally do not involve ethical concerns. True
False
Answer:
False
Question:
Construction management is a concept that is susceptible to overselling. True False
Answer:
True
Question:
Failure to provide quality services is a business and not an ethical question. True False
Answer:
False
Question:
Contracting for adequate fees is both a business and an ethical issue. True False
Answer:
True
Question:
The ethics of the CM profession focus primarily on a CM's relationships in dealing with its clients.
True False
Answer:
True
, Question:
The possible approaches for delivering a project are virtually unlimited. A key reason for such
variations is: A) The different roles that can be assumed by project participants. B) Different forms
of contracts and methods of compensation that can be used. C) The different levels of care,
responsibility, and risks assumed by the parties involved. D) All of the above.
Answer:
D) All of the above
Question:
The traditional delivery system is characterized by executing the major phases of a project in: A) An
overlapping concept B) A linear sequence C) A fast track method D) All of the above
Answer:
B) A linear sequence
Question:
A key advantage of the traditional delivery approach is: A) With the traditional delivery system, the
cost of the construction phase is known before construction starts. B) Facility features are fully
determined & specified. C) When the construction contract is signed, the major risk belongs to the
contractor. D) All of the above
Answer:
B) Facility features are fully determined & specified.
Question:
Design-build and at-risk construction management delivery systems allow the option to fast-track or
phase a project. True False
Answer:
True
CMIT Exam Questions and Answers Verified
Solutions Latest Update 2026/2027
Question:
Construction management had its beginnings in the early to mid-1960's. Which of the following
factors contributed to the initial use of this delivery system? A) The need to reduce the overall time
and cost associated with project delivery. B) The increasing cost of money and the unpredictability
of project funding streams. C) The changing role of the general contractor and the increasing
numbers of specialty trade contractors. D) All of the above.
Answer:
D) All of the above.
Question:
The General Services Administration was the first federal agency to use construction management.
Answer:
True
Question:
The General Services Administration, the Department of Health, Education and Welfare (now
HHS), and the Veterans Administration ran into similar difficulties in the use of construction
management. Which of the following was/were common problems for all three agencies? A)
Funding restrictions B) Claims C) Change conditions D) All of the above
Answer:
D) All of the above
Question:
CMAA was formed and incorporated 1982 with its primary focus being the growth and
development of the construction management profession.
Answer:
,True
Question:
The CMAA Construction Management Standards of Practice is intended as a guide to the range of
services that constitute professional construction management. They seek to meet the documented
need for definitions of what construction management services are, without unduly structuring the
methodologies by which those services are provided by the CM.
Answer:
True
Question:
The goals of the Construction Management Association of America (CMAA) include: A) Setting
standards and developing contract documents for construction management practice. B) Expanding
the understanding of the construction management concept and its use in the marketplace. C)
Advocacy for construction management in the legislative, regulatory, and judicial arenas of federal,
state, and local governments. D) All of the above.
Answer:
D) All of the above
Question:
The fact that an individual is certified or licensed in any other profession does not, per se, establish
him/her as a qualified CM. True False
Answer:
True
Question:
Certification as a CM means the construction management practitioner has "state of the art"
knowledge and capability to practice construction management. True False
Answer:
False
,Question:
Recruiting and training are business matters and normally do not involve ethical concerns. True
False
Answer:
False
Question:
Construction management is a concept that is susceptible to overselling. True False
Answer:
True
Question:
Failure to provide quality services is a business and not an ethical question. True False
Answer:
False
Question:
Contracting for adequate fees is both a business and an ethical issue. True False
Answer:
True
Question:
The ethics of the CM profession focus primarily on a CM's relationships in dealing with its clients.
True False
Answer:
True
, Question:
The possible approaches for delivering a project are virtually unlimited. A key reason for such
variations is: A) The different roles that can be assumed by project participants. B) Different forms
of contracts and methods of compensation that can be used. C) The different levels of care,
responsibility, and risks assumed by the parties involved. D) All of the above.
Answer:
D) All of the above
Question:
The traditional delivery system is characterized by executing the major phases of a project in: A) An
overlapping concept B) A linear sequence C) A fast track method D) All of the above
Answer:
B) A linear sequence
Question:
A key advantage of the traditional delivery approach is: A) With the traditional delivery system, the
cost of the construction phase is known before construction starts. B) Facility features are fully
determined & specified. C) When the construction contract is signed, the major risk belongs to the
contractor. D) All of the above
Answer:
B) Facility features are fully determined & specified.
Question:
Design-build and at-risk construction management delivery systems allow the option to fast-track or
phase a project. True False
Answer:
True