1|P a g e
NORTH CAROLINA ELECTRICAL INSPECTOR LEVEL
II CERTIFICATION ACTUAL EXAM PREP 2026 ALL
QUESTIONS AND CORRECT DETAILED ANSWERS
WITH RATIONALES ALREADY A GRADED WITH
EXPERT FEEDBACK |BRAND NEW! HIGHLY
RECOMMENDED
1. According to the North Carolina Administrative Code, what is the
minimum passing score required on the Electrical Level II certification
examination?
A) 60%
B) 70%
C) 75%
D) 80%
Rationale: The North Carolina Code Officials Qualification Board
requires a minimum score of 70% to pass the examination and receive
certification.
2. A Level II Electrical Inspector in North Carolina is authorized to
inspect electrical installations in which types of structures?
A) Only individual residential dwelling units
B) All types of construction up to 60,000 square feet
C) Only commercial structures under 100,000 square feet
D) All types of construction without square footage limitations
Rationale: The Electrical Level II certification is designed for code
enforcement officials responsible for inspecting electrical installations
in all types of construction up to 60,000 square feet.
,2|P a g e
3. The North Carolina Electrical Inspector Level II examination is an
open-book exam. Which of the following references is ALLOWED in
the examination center?
A) Any published electrical code commentary
B) The 2017 National Electrical Code with North Carolina
Amendments
C) The 2023 National Electrical Code
D) A personal notebook with handwritten notes
Rationale: The examination is open-book, but only the approved
references listed in the examination bulletin are allowed. The 2017
National Electrical Code with North Carolina Amendments is a
permitted reference. Personal notebooks are not permitted.
4. According to NC General Statutes, who has the authority to issue a
stop-work order for an electrical installation that poses an immediate
hazard?
A) Only the local building official
B) A certified Level II Electrical Inspector
C) Only the State Electrical Inspector
D) The electrical contractor on the project
Rationale: A Level II Electrical Inspector in North Carolina may issue
a stop-work order for unsafe electrical installations. This authority is
granted under the North Carolina Administrative Code and General
Statutes pertaining to code enforcement officials.
5. An electrical contractor is installing service equipment in a
commercial building. The inspector notes that the service disconnecting
means is located in a storage room that is not dedicated to electrical
equipment. What is the MOST appropriate action?
A) Approve the installation as long as the room is accessible
B) Issue a correction notice requiring the service equipment to be
,3|P a g e
relocated to a dedicated space
C) Issue a stop-work order
D) Recommend that the contractor install a lock on the storage room
door
Rationale: Service equipment must be located in a dedicated space that
is readily accessible and not used for storage. The inspector should
issue a correction notice requiring compliance with NEC Article 230
and NC amendments.
6. Under the North Carolina Administrative Code, which of the
following is a requirement for maintaining an Electrical Inspector Level
II certification?
A) Passing a refresher exam every two years
B) Completing continuing education hours related to the National
Electrical Code
C) Submitting a new application annually
D) Completing a minimum of 50 inspections per year
Rationale: All municipal and county electrical inspectors must be
certified by the NC Code Officials Qualification Board and must
complete continuing education hours related to the National Electrical
Code.
7. A Level II Electrical Inspector is reviewing plans for a new restaurant.
The plans show a 400-ampere, 120/240-volt, single-phase service.
Which of the following is the MINIMUM size grounding electrode
conductor required for this service, assuming copper conductors?
A) #6 AWG
B) #4 AWG
C) #2 AWG
D) #1/0 AWG
, 4|P a g e
Rationale: According to NEC Table 250.66, for a 400-ampere service,
the minimum size grounding electrode conductor for copper is #2
AWG. This applies to services up to 400 amperes with copper
conductors.
8. An inspector is examining the grounding electrode system at a new
commercial building. The building has a concrete-encased electrode
(Ufer ground) installed in the footing. Which of the following is a
requirement for this electrode to be acceptable?
A) The electrode must be at least 10 feet of #4 copper wire
B) The electrode must be at least 20 feet of #4 or larger steel
reinforcing bar
C) The electrode must be at least 10 feet of copper-clad steel rod
D) The electrode must be at least 20 feet of bare copper wire
Rationale: A concrete-encased electrode (Ufer ground) must consist of
at least 20 feet of bare copper wire or steel reinforcing bar (#4 or
larger) located within and near the bottom of the concrete footing, as
per NEC 250.52(A)(3).
9. A commercial building has a 600-ampere, 208Y/120-volt, three-phase
service. The service-entrance conductors are aluminum. According to
NEC Table 310.15(B)(16), what is the MINIMUM size of aluminum
conductors required for this service, assuming 75°C terminals?
A) 300 kcmil
B) 400 kcmil
C) 500 kcmil
D) 600 kcmil
Rationale: According to NEC Table 310.15(B)(16), a 600-ampere
service using aluminum conductors at 75°C requires 500 kcmil
conductors, which have an ampacity of 500 amperes (or 380 amperes
for 400 kcmil). The 500 kcmil is needed for 600 amps.
NORTH CAROLINA ELECTRICAL INSPECTOR LEVEL
II CERTIFICATION ACTUAL EXAM PREP 2026 ALL
QUESTIONS AND CORRECT DETAILED ANSWERS
WITH RATIONALES ALREADY A GRADED WITH
EXPERT FEEDBACK |BRAND NEW! HIGHLY
RECOMMENDED
1. According to the North Carolina Administrative Code, what is the
minimum passing score required on the Electrical Level II certification
examination?
A) 60%
B) 70%
C) 75%
D) 80%
Rationale: The North Carolina Code Officials Qualification Board
requires a minimum score of 70% to pass the examination and receive
certification.
2. A Level II Electrical Inspector in North Carolina is authorized to
inspect electrical installations in which types of structures?
A) Only individual residential dwelling units
B) All types of construction up to 60,000 square feet
C) Only commercial structures under 100,000 square feet
D) All types of construction without square footage limitations
Rationale: The Electrical Level II certification is designed for code
enforcement officials responsible for inspecting electrical installations
in all types of construction up to 60,000 square feet.
,2|P a g e
3. The North Carolina Electrical Inspector Level II examination is an
open-book exam. Which of the following references is ALLOWED in
the examination center?
A) Any published electrical code commentary
B) The 2017 National Electrical Code with North Carolina
Amendments
C) The 2023 National Electrical Code
D) A personal notebook with handwritten notes
Rationale: The examination is open-book, but only the approved
references listed in the examination bulletin are allowed. The 2017
National Electrical Code with North Carolina Amendments is a
permitted reference. Personal notebooks are not permitted.
4. According to NC General Statutes, who has the authority to issue a
stop-work order for an electrical installation that poses an immediate
hazard?
A) Only the local building official
B) A certified Level II Electrical Inspector
C) Only the State Electrical Inspector
D) The electrical contractor on the project
Rationale: A Level II Electrical Inspector in North Carolina may issue
a stop-work order for unsafe electrical installations. This authority is
granted under the North Carolina Administrative Code and General
Statutes pertaining to code enforcement officials.
5. An electrical contractor is installing service equipment in a
commercial building. The inspector notes that the service disconnecting
means is located in a storage room that is not dedicated to electrical
equipment. What is the MOST appropriate action?
A) Approve the installation as long as the room is accessible
B) Issue a correction notice requiring the service equipment to be
,3|P a g e
relocated to a dedicated space
C) Issue a stop-work order
D) Recommend that the contractor install a lock on the storage room
door
Rationale: Service equipment must be located in a dedicated space that
is readily accessible and not used for storage. The inspector should
issue a correction notice requiring compliance with NEC Article 230
and NC amendments.
6. Under the North Carolina Administrative Code, which of the
following is a requirement for maintaining an Electrical Inspector Level
II certification?
A) Passing a refresher exam every two years
B) Completing continuing education hours related to the National
Electrical Code
C) Submitting a new application annually
D) Completing a minimum of 50 inspections per year
Rationale: All municipal and county electrical inspectors must be
certified by the NC Code Officials Qualification Board and must
complete continuing education hours related to the National Electrical
Code.
7. A Level II Electrical Inspector is reviewing plans for a new restaurant.
The plans show a 400-ampere, 120/240-volt, single-phase service.
Which of the following is the MINIMUM size grounding electrode
conductor required for this service, assuming copper conductors?
A) #6 AWG
B) #4 AWG
C) #2 AWG
D) #1/0 AWG
, 4|P a g e
Rationale: According to NEC Table 250.66, for a 400-ampere service,
the minimum size grounding electrode conductor for copper is #2
AWG. This applies to services up to 400 amperes with copper
conductors.
8. An inspector is examining the grounding electrode system at a new
commercial building. The building has a concrete-encased electrode
(Ufer ground) installed in the footing. Which of the following is a
requirement for this electrode to be acceptable?
A) The electrode must be at least 10 feet of #4 copper wire
B) The electrode must be at least 20 feet of #4 or larger steel
reinforcing bar
C) The electrode must be at least 10 feet of copper-clad steel rod
D) The electrode must be at least 20 feet of bare copper wire
Rationale: A concrete-encased electrode (Ufer ground) must consist of
at least 20 feet of bare copper wire or steel reinforcing bar (#4 or
larger) located within and near the bottom of the concrete footing, as
per NEC 250.52(A)(3).
9. A commercial building has a 600-ampere, 208Y/120-volt, three-phase
service. The service-entrance conductors are aluminum. According to
NEC Table 310.15(B)(16), what is the MINIMUM size of aluminum
conductors required for this service, assuming 75°C terminals?
A) 300 kcmil
B) 400 kcmil
C) 500 kcmil
D) 600 kcmil
Rationale: According to NEC Table 310.15(B)(16), a 600-ampere
service using aluminum conductors at 75°C requires 500 kcmil
conductors, which have an ampacity of 500 amperes (or 380 amperes
for 400 kcmil). The 500 kcmil is needed for 600 amps.