CADE FINAL EXAM REVIEW WALMART
STORMWATER MANAGEMENT QUESTIONS
WITH CORRECT ANSWERS LATEST 2025-2026
UPDATE
The Clean Water Act - Answer-The 1970s federal law that set into place
the regulation of stormwater.
NPDES - Answer-Requirements for managing storm water activity on a
construction site.
The Notice of Termination (NOT) can be filed when - Answer-All
construction activity (inside and outside) is complete and permanent
stabilization has been verified as adequate to meet permit requirements.
All of the following must occur before construction starts, except:
1. Prepare the SWPPP
2. Determine the Operator(s)
3. Submit the Notice of Intent (NOI)
4. Submit the Notice of Termination (NOT) - Answer-4. Submit the
Notice of Termination (NOT).
, Which of the following is NOT a beneficial use of water?
1. Swimming
2. Drinking
3. Flushing a spill down a storm drain
4. Industrial and agricultural water supply - Answer-3. Flushing a spill
down a storm drain.
When installing and maintaining a check dam, make sure:
1. Stormwater is directed around the check dam
2. Void spaces are filled with sediment
3. The low point (overflow) of the check dam is in the middle of the
channel
4. The high point of the check dam is in the middle of the channel -
Answer-3. The low point (overflow) of the check dam is in the middle of
the channel.
To reduce the possibility of undercutting in channels, you should:
1. Stabilize diversions and swales within 21-days of construction
2. Add mulch and straw
3. Install filter fabric under rock and similar materials placed within the
stormwater conveyance
STORMWATER MANAGEMENT QUESTIONS
WITH CORRECT ANSWERS LATEST 2025-2026
UPDATE
The Clean Water Act - Answer-The 1970s federal law that set into place
the regulation of stormwater.
NPDES - Answer-Requirements for managing storm water activity on a
construction site.
The Notice of Termination (NOT) can be filed when - Answer-All
construction activity (inside and outside) is complete and permanent
stabilization has been verified as adequate to meet permit requirements.
All of the following must occur before construction starts, except:
1. Prepare the SWPPP
2. Determine the Operator(s)
3. Submit the Notice of Intent (NOI)
4. Submit the Notice of Termination (NOT) - Answer-4. Submit the
Notice of Termination (NOT).
, Which of the following is NOT a beneficial use of water?
1. Swimming
2. Drinking
3. Flushing a spill down a storm drain
4. Industrial and agricultural water supply - Answer-3. Flushing a spill
down a storm drain.
When installing and maintaining a check dam, make sure:
1. Stormwater is directed around the check dam
2. Void spaces are filled with sediment
3. The low point (overflow) of the check dam is in the middle of the
channel
4. The high point of the check dam is in the middle of the channel -
Answer-3. The low point (overflow) of the check dam is in the middle of
the channel.
To reduce the possibility of undercutting in channels, you should:
1. Stabilize diversions and swales within 21-days of construction
2. Add mulch and straw
3. Install filter fabric under rock and similar materials placed within the
stormwater conveyance