1. Who must a construction superintendent consider when evaluating options to improve
project performance? - Correct Answers a. All project stakeholders
1. The NSPE Fundamental Canons and Poole's Rules both include which quality as essential in
principled leadership? - Correct Answers a. Integrity
1. Which individual would be the best candidate for training as a construction superintendent? -
Correct Answers a. Candidate C is a good decision maker and wants more leadership
responsibility.
1. Which principle should be adopted in your role as a leader and superintendent? - Correct
Answers a. Success always belongs to the team.
1. A newly certified superintendent will oversee the site preparation phase for a major
commercial build. On the first day of the job, what approach is recommended? - Correct
Answers a. Make a list of everything that must happen within the next six weeks.*
1. What's the most effective way to reduce communication gaps among the crew during the
course of the workday? - Correct Answers a. Walk the jobsite and ask questions.
1. Holding team members accountable is an element of which leadership behavior? - Correct
Answers a. Setting expectations and consequences
1. What must be the top priority when making decisions on the jobsite? - Correct Answers a.
Keeping people safe
,1. What's a recommended strategy for keeping meetings productive and on track? - Correct
Answers a. Share the agenda before the meeting begins
When is using informal language a good choice on the jobsite? - Correct Answers a. When
conducting a daily job walk
What's an important purpose of creating your own leadership development plan? - Correct
Answers a. To help you in navigating complex decisions
1. Who determines construction project requirements for measuring quality? - Correct Answers
a. Owner/designer
1. Which item should be included in your project's quality plan? - Correct Answers a. Project-
specific standards
1. What is the first step in a QA process? - Correct Answers a. Define specifications and
applicable codes
1. What is the focus of the QC process in construction - Correct Answers a. Locating defects
1. What is the superintendent's primary role in managing quality? - Correct Answers a. To
ensure frontline supervisors and specialty contractors understand the quality plan
1. A project's quality plan includes a 20-item electrical checklist based on National Electrical
Code guidelines. How would the superintendent use this checklist? - Correct Answers a. To
manage the installation team
1. What is an example of a definable feature of work for a warehouse construction project? -
Correct Answers a. Excavation work on a greenfield site
, 1. Who requires access to the specifications provided by the project designer? - Correct Answers
a. All personnel (including field personnel)
1. Which type of specification lists the precise materials that must be used in the project, such
as requiring Class-B pipe in a commercial project? - Correct Answers a. Perspective-based
1. What is the role of the American National Standards Institute (ANSI) and the American
Society for Testing and Materials (ASTM) in the construction process? - Correct Answers a.
Establishes codes, standards, and recognized specifications
1. How should a project-specific quality control plan be organized? - Correct Answers a.
Organize in three stages: pre-construction, construction, and post-construction
1. What constitutes non-conformance work? - Correct Answers a. Work failing to meet
contractual quality standards
1. The contract requires an HDPE pipe-bent strap test, as well as hydrostatic, leak, water
pressure, and air testing for the water distribution system. Which document lists these tests, as
well as their frequency, target date, and supervisor? - Correct Answers a. Inspection and test
plan
1. Soil testing and site condition inspections take place at which stage in the construction
process? - Correct Answers a. Pre-construction
1. What three interdependent elements form the basis of the quality triangle? - Correct
Answers a. Quality, time, and cost
1. In terms of scheduling, what is the key skill required for construction superintendents at
projects of all sizes? - Correct Answers a. Ability to use the schedule to drive the project