Topics: Arizona ROC Requirements, Excavation Fundamentals, OSHA Safety, Utility
Locating, Soil Classification & Site Preparation
Question 1
Before beginning any excavation project in Arizona, what is the most important action a
licensed CR2 contractor should complete to reduce the risk of striking underground utilities?
A. Begin excavation during daylight hours only.
B. Notify Arizona 811 (Blue Stake) and verify that underground utilities have been
properly located and marked before excavation begins.
C. Increase the excavation depth slowly.
D. Use only hand tools throughout the project.
Correct Answer: B
Rationale: Arizona law requires contractors to request utility locates before excavation.
Contacting Arizona 811 (Blue Stake) helps prevent damage to underground facilities and
protects worker safety.*
Question 2
The primary purpose of grading a construction site is to:
A. Increase equipment fuel efficiency.
B. Improve soil color.
C. Establish the required elevations, drainage patterns, and stable foundation for
construction.
D. Reduce concrete curing time.
Correct Answer: C
Rationale: Proper grading ensures water drains correctly, structures are built on stable
ground, and project specifications are achieved.*
,Question 3
Under OSHA excavation standards, a trench is generally defined as:
A. Any hole deeper than 2 feet.
B. Any excavation less than 50 feet wide.
C. A narrow excavation in which the depth is greater than the width and the width at
the bottom does not exceed 15 feet (4.6 m).
D. Any excavation requiring heavy equipment.
Correct Answer: C
Rationale: OSHA distinguishes trenches from other excavations based on width and depth
characteristics.*
Question 4
Which soil classification is generally considered the most stable under OSHA excavation
standards?
A. Type C
B. Type B
C. Mixed soil
D. Type A
Correct Answer: D
Rationale: Type A cohesive soil has the greatest strength when it has not been disturbed or
compromised.*
Question 5
A competent person on an excavation project is responsible for:
A. Preparing payroll.
B. Inspecting excavations, identifying hazards, and taking prompt corrective action
when unsafe conditions are found.
, C. Operating every piece of heavy equipment.
D. Approving building permits.
Correct Answer: B
Rationale: OSHA requires a competent person to inspect excavations daily and after
hazard-increasing events.*
Question 6
The primary purpose of a trench protective system is to:
A. Improve fuel economy.
B. Increase excavation speed.
C. Protect workers from cave-ins and soil collapse.
D. Reduce grading costs.
Correct Answer: C
Rationale: Cave-ins are among the leading causes of fatalities in excavation work, making
protective systems essential.*
Question 7
Before operating an excavator, the operator should first:
A. Increase engine speed immediately.
B. Conduct a complete pre-operation inspection following the manufacturer's
recommendations.
C. Fill the bucket with soil.
D. Extend the boom completely.
Correct Answer: B
Rationale: Daily inspections help identify mechanical defects before equipment is placed
into service.*