Aaron is working with a few team members on the work breakdown structure.
Sherry, from a different project team, continually interrupts the meeting to ask
for their status updates. Aaron has polite declined and says there's no reason
for her to require any updates and believe she has a personal interest in the
project. What should you do as the project manager? - Answer✔✔-Speak to
Sherry separately
You are currently analyzing the communication requirements for a project you
are managing. You need to identify the main expectations of each of the
internal stakeholders to ensure that their communication needs are satisfied.
Which resource should you consult to locate this information? - Answer✔✔-
Stakeholder register
Your team is made up of a variety of cultures and nationalities. It seems each
member has aligned their expectations separately with customer, the end user,
or the vendor. The team wants to satisfy everyone with an exceptional product,
but the team has a hard time agreeing on what the first sprint will cover. What
,is the source of the conflict? - Answer✔✔-Different stakeholder interests
during the forming stage
You are working on a project to build an encrypted messaging platform. The
platform has undergone several iterations and recently your organization has
expanded. As part of this expansion you will be taking on two junior
developers. You have been asked to bring them up to speed on the project
quickly and ensure that they get all the support required for them to move into
senior developer positions in due time. You want to make sure that their needs
are met. What should you do? - Answer✔✔-Set up a regularly scheduled
meeting with the junior staff to discuss performance and improvement
You need to ensure planned expenditures never exceed planned funds-on-
hand. Which method should you use to achieve this? - Answer✔✔-Funding
limit reconciliation
Frank is a new project team member with some project experience in all areas
of project management, but specializing in procurements. The project has
received proposals from different vendors. Frank has been assigned the task to
determine if the cost estimates of the procurement items provided by one of
the qualified vendors are reasonable. Which action should he do FIRST? -
Answer✔✔-Obtain an independent cost estimate for the procurement items
from a professional external estimator.
During a sprint review, you review the growing product backlog. The product
owner continues to add new features to ensure we exceed customer
expectations. They have committed to the customer and now team members
are accusing each other for the negative impact to the schedule. What is the
reason for the conflict? - Answer✔✔-Gold plating
,Glen is managing a team of software designers. He receives an update on the
status of the design plans from one of the lead designers via email. Based on
the information provided in the update and the project schedule, Glen has
determined some project objectives will exceed the risk thresholds set by the
organization. What should Glen do FIRST? - Answer✔✔-Advise the project
sponsor of the situation.
You are discussing the various types of project stakeholders with one of the
junior project managers in your organization. You are in the process of
identifying the responsibilities of the different levels of management
associated with projects. Which distinguishing factors can you tell them are
inherent to a portfolio manager? - Answer✔✔-Provides governance for a group
of projects, leads the project selection process, identifies a project's return on
investment
Helen, Irene, and John make up an organization's review committee for a
project they are working on. They have received responses from various
vendors to the procurement document package and are formally reviewing
prospective vendors according to their capabilities to successfully complete the
conditions of the contract. They have been authorized to select vendors prior
to senior management approval. Which action is the review committee
currently undertaking? - Answer✔✔-Proposal evaluation
Wayne is leading a project team that has experienced team members working
in two different buildings across the city from each other. After reviewing this
month's performance reports, Wayne has noticed a significant drop in
performance and an increase in issues that are not being addressed. Wayne
takes action by inviting the team members out for drinks in the evening to
relieve some stress. A discussion occurs during the evening between Wayne
and the team members regarding the team's declining progress and the
increase in unresolved issues. After actively listening to the team members,
, Wayne has to decide how to address the situation. Which action should Wayne
take? - Answer✔✔-Implement a solution that involves colocation
You work for an organization that has a strong matrix structure. They are
looking for ideas for innovative projects that will help them stay competitive in
the current market. Which action is the FIRST thing that you should do to
develop relevant ideas? - Answer✔✔-Review your organization's strategic goals
Your project team has just finished the final user story in this iteration. The
project is being tested prior to being released to production. During testing, a
junior developer work came back as non-compliant and will need to be re-
worked. The junior developer was confident in the solution and the re-work is
going to impact the value the team can deliver in this iteration. What should
you do? - Answer✔✔-Sit down with the junior developer and coach them on
how they can improve their code
You have taken over as the project manager for one of the top golf equipment
producers in the world. The previous project manager was overseeing the
development of this year's club models. The budget they created was short
sighted and based upon the previous year's numbers. You have determined
that, due to material costs, the approved budget will need to be increased.
Which action is required to increase the budget? - Answer✔✔-Initiate a change
request
An important project document is missing from the shared folder since
yesterday. Most of team members are indirectly conveying that "The document
is not deleted by me".