Question: (immovable) can refer to the real estate itself, or to various types of interest in real estate.
Land (L) & Improvements to land: Buildings (B), Structures (S), & Linear Systems (LS),
which includes utility systems and permanently attached real property installed equipment
(RPIE) that are part of building structure.
Correct Answer: Real Property
Question: Real Property In- stalled Equip- ment (RPIE)
Correct Answer: Essential to function of the facility, normally installed during construction, per-
manently attached, if not RPIE then consider unit personal property (Furnish-
ing/Equipment).
Question: Responsible for all real property assets under installation control regardless of who
funded/maintains the construction. They maintain DAF real property inventory (RPI) in
ASPR. Assigns customer to assets allocations.
Correct Answer: Real Property Of- fice
Question: Accountable Property System of Record (APSR)
Correct Answer: NexGen IT; DAF inventory of their government assets (includes RPIE).
Question: 7115 Report
Correct Answer: Current inventory within account database; Own, lease, manage; Facility numbers,
cat codes, square footages.
Question: 1354 Required
Correct Answer: New facility; Increase in existing facility; Useful life of facility increase (Major
system upgrade).
Question: Capital Improve- ment to existing facilities
Correct Answer: Increase useful life, efficiency, capacity, size.
, Question: FIAR Audit
Correct Answer: "Baselining" requirements: annual E&C of buildings, structures, linear structure,
PRV & PISD Reconciliation.
Question: Project Manage- ment
Correct Answer: Process to systematically accomplish specific tasks.
Question: PM Goals of time, cost, and quality
Correct Answer: High quality, on time, on budget, same scope.
Question: Tradeoffs be- tween PM goals
Correct Answer: Can't change all 3 goals at once.
Question: Lifestyle Impact
Correct Answer: Later in project, scope changes are more expensive.
Question: Primary Stake- holders for AF Capital Project
Correct Answer: PM, user, design team, KTR's, contracting officer, coordinating agencies senior
leaders.
Question: Distinct Phases in lifecycle of pro- ject
Correct Answer: Plan & Program, design, construction, close-out.
Question: Civil Engineers role through each phase of project manage- ment
Correct Answer: Define and validate the requirement; Siting and planning considerations; Generate
1391; Coordinate design reviews; Quality assurance/control and technical repre-
sentative for contract compliance; Final inspections; Real property capitalization.
Question: Work Statement
Correct Answer: Defines requirements with measurable outcomes.
Question: Good work state- ment
Correct Answer: Clearly defines requirements, concisely communicates expectations.