MODULE TRIPLE CONSTRAINTS OF PROJECTS
TRIPLE CONSTRAINTS OF PROJECTS
Step 1 of 1
Question 1 of 15
True or False.
A cost of business includes travel expenses and technology investments
necessary for the project.
True
False
Correct. A cost of business is an expense that is not part of carrying
out the project. Costs incurred by contractors preparing a bid, hiring
personnel, or purchasing equipment that will be used following
completion of the project cannot be charged to the project. Costs
incurred for the project should be charged to the project.
Question 2 of 15
Which of the following occurs when there are incremental additions to the
project scope that are not subject to the formal scope change process?
https://wgu-nx.acrobatiq.com/courseware/summative-assessment/wgu_pm_nov15/u3_m6_quiz/5baea0af0000090ef004821a 1/8
, 10/7/2018 Triple Constraints of Projects | Acrobatiq
Float time
Scope creep
Triple constraint
Statement of work
Correct! Scope creep occurs when there are any incremental
additions to the project scope that are not subject to the formal
scope change process.
Question 3 of 15
Which of the following defines the product of the project and contains
information such as the project objectives and project deliverables?
cost of business
PERT chart
Gantt chart
project scope
Correct! The project scope defines the product of the project and
contains information such as the project objectives and project
deliverables.
Question 4 of 15
Which of the following is a timeline that specifies when the project begins and
when it is supposed to end?