EVA Process Step 1
Collect measures from project records:
1. AC - Actual Cost
2. EV - Earned Value
3. PV - Planned Value
4. BAC - Budget at Completion
EVA Process Step 2
Calculate Variances:
1. CV - Cost Variance
2. SV - Schedule Variance
3. PCIB - Percent complete index budget
EVA Process Step 3
Calculate Performance Factors
1. CPI - Cost Performance Index
2. SPI - Schedule Performance Index
EVA Process Step 4
Calculate Estimates or Identifying Performance Factors
1. ETC - Estimate to completion
2. EAC - Estimate at completion
3. TCPI - To complete performance Index
4. PCIB - Percent complete index budget or
PCIC - (Percent complete index - cost)
Equation to determine if a project is meeting budget expectations
Cost Variance
CV = EV-AC
(Earned Value - Actual Cost)
Equation to determine if a project is meeting schedule expectations
Schedule Variance
SV = EV-PV
(Earned Value - Planned Value)
CPI
, C722 - Project Management, Terms & Examples
Cost performance index
Measures cost efficiency
CPI = EV/AC
(Earned Value / Actual Cost)
CPI > 1 or 100%
CPI < 1 or 100%
CPI>1
Project team is completing more work at less cost than expected
CPI<1
Project team is accomplishing less work for the money spent and is
behind budget
SPI
Schedule performance index
Measures time efficiency
SPI = EV/PV
(Earned Value / Planned Value)
SPI > 1 or 100%
SPI < 1 or 100%
SPI > 1
Project team is completing more work in less time than expected
SPI < 1
Project team is completing less work than what is required in the
time allowed and is behind schedule
What is TCPI
To complete performance index
What the CPI (cost performance index) will need to be for the
remainder of the project if the team intends to finish on budget
TCPI Equation