Fundamentals) 2026\2027
What is a Man-Day?
- correct answer Unit of work performed by one person in 8 hours
Define what a Project Scope is.
- correct answer - Project Supervisor and Crew Leads review the plans with the drawings
- Project Sup and Crew Leads prep a project package scope sheet and send it to S3
- Project sups create a project scope sheet with information and pictures of the site
Define Direct Labor
- correct answer All labor, in the field or shop, directly related to the assigned task
Define Indirect Labor
- correct answer All labor in support of a project but usually doesn't produce an end product
Define Readiness and Training
- correct answer Preparations for military exercises and disaster preparedness.
What does a Delay Factor do?
- correct answer It calculate how many extra Man-Days are needed for a project
What is the Man-Day Capability?
- correct answer - MC= DL x WD x ME x AF
- MC: Total Man-Day capiblity
- DL: Number of Direct Labor Personnel on a project
- WD: Number of Workdays
- ME: Man-Day Equivalent (number of hours ACTUALLY worked)