Written by students who passed Immediately available after payment Read online or as PDF Wrong document? Swap it for free 4.6 TrustPilot
logo-home
Document preview thumbnail
Preview 4 out of 33 pages
Exam (elaborations)

New Mexico EL-1J Electrical Distribution Journeyman Exam Practice

Document preview thumbnail
Preview 4 out of 33 pages

New Mexico EL-1J Electrical Distribution Journeyman Exam Practice QUESTION 1 A journeyman electrician is planning to work on a 25 kV overhead distribution line. According to OSHA 1910.269, what is the PRIMARY factor that determines the minimum approach distance? A) The phase-to-ground voltage only B) The phase-to-phase voltage and the type of work being performed C) The maximum anticipated transient overvoltage and phase-to-phase voltage D) The ambient temperature and humidity conditions Answer: C Rationale: OSHA 1910.269 Table 1 establishes minimum approach distances based on both the phase-to-phase voltage and the maximum anticipated transient overvoltage. This is a critical safety consideration because transient overvoltages can significantly increase the risk of arc flash and shock. Option A is incorrect because phase-to-ground alone is insufficient. Option B omits the transient overvoltage factor, which is essential for determining safe distances. Option D is incorrect as environmental conditions are not primary determinants of MAD. QUESTION 2 A distribution line crew is replacing a crossarm on a 7.2 kV phase-to-ground system. The supervisor needs to determine the appropriate MAD. What should they use as the reference voltage? A) 7.2 kV B) 12.47 kV C) 14.4 kV D) 25 kV Answer: B Rationale: OSHA 1910.269 Table 1 uses phase-to-phase voltage for determining minimum approach distances. For a 7.2 kV phase-to-ground system in a three-phase wye configuration, the phase-to-phase voltage is 7.2 kV × √3 = 12.47 kV. Option A would be incorrect because it represents the phase-to-ground voltage only. Option C (14.4 kV) and Option D (25 kV) are arbitrary values not derived from the given system parameters. QUESTION 3 A utility company is designing a new overhead distribution line through a residential neighborhood. The line will operate at 34.5 kV phase-to-phase. According to NESC Table 232-1, what is the required minimum vertical clearance over a residential street? A) 15.5 ft B) 18.5 ft C) 21.0 ft D) 24.0 ft Answer: D Rationale: NESC Table 232-1 specifies clearance requirements based on voltage. For voltages between 22 kV and 50 kV over streets and alleys, the required clearance is 24 ft. Option A (15.5 ft) applies to voltages below 0-50 kV in some jurisdictions but is not correct for this voltage. Option B (18.5 ft) is for 0-50 kV in specific situations but not for 34.5 kV. Option C (21.0 ft) is not specified for this voltage range in the table. QUESTION 4 A maintenance crew needs to enter a manhole containing de-energized but unverified electrical equipment. What additional step does OSHA 1910.269 require beyond the lockout/tagout procedure? A) Atmospheric testing every 15 minutes B) Verification of the de-energized state before entry C) Continuous ventilation of the manhole D) A standby employee with a rescue harness Answer: B Rationale: OSHA 1910.269 requires that before employees enter manholes or vaults containing exposed energized electrical equipment, the equipment must be de-energized AND verification of the de-energized state must be completed. Verification is a critical safety step that ensures the equipment is truly de-energized. Option A relates to confined space requirements but is not the primary requirement for de-energized equipment. Option C is a general safety consideration but not the specific OSHA requirement. Option D is a rescue requirement but not the verification requirement.

Content preview

New Mexico EL-1J Electrical Distribution Journeyman Exam
Practice



QUESTION 1



A journeyman electrician is planning to work on a 25 kV overhead
distribution line. According to OSHA 1910.269, what is the PRIMARY factor
that determines the minimum approach distance?



A) The phase-to-ground voltage only

B) The phase-to-phase voltage and the type of work being performed

C) The maximum anticipated transient overvoltage and phase-to-phase
voltage

D) The ambient temperature and humidity conditions



Answer: C



Rationale: OSHA 1910.269 Table 1 establishes minimum approach
distances based on both the phase-to-phase voltage and the maximum
anticipated transient overvoltage. This is a critical safety consideration
because transient overvoltages can significantly increase the risk of arc
flash and shock. Option A is incorrect because phase-to-ground alone is
insufficient. Option B omits the transient overvoltage factor, which is
essential for determining safe distances. Option D is incorrect as
environmental conditions are not primary determinants of MAD.




QUESTION 2



A distribution line crew is replacing a crossarm on a 7.2 kV phase-to-
ground system. The supervisor needs to determine the appropriate MAD.
What should they use as the reference voltage?

,A) 7.2 kV

B) 12.47 kV

C) 14.4 kV

D) 25 kV



Answer: B



Rationale: OSHA 1910.269 Table 1 uses phase-to-phase voltage for
determining minimum approach distances. For a 7.2 kV phase-to-ground
system in a three-phase wye configuration, the phase-to-phase voltage is
7.2 kV × √3 = 12.47 kV. Option A would be incorrect because it represents
the phase-to-ground voltage only. Option C (14.4 kV) and Option D (25 kV)
are arbitrary values not derived from the given system parameters.




QUESTION 3



A utility company is designing a new overhead distribution line through a
residential neighborhood. The line will operate at 34.5 kV phase-to-phase.
According to NESC Table 232-1, what is the required minimum vertical
clearance over a residential street?



A) 15.5 ft

B) 18.5 ft

C) 21.0 ft

D) 24.0 ft



Answer: D



Rationale: NESC Table 232-1 specifies clearance requirements based on
voltage. For voltages between 22 kV and 50 kV over streets and alleys,
the required clearance is 24 ft. Option A (15.5 ft) applies to voltages below

,0-50 kV in some jurisdictions but is not correct for this voltage. Option B
(18.5 ft) is for 0-50 kV in specific situations but not for 34.5 kV. Option C
(21.0 ft) is not specified for this voltage range in the table.




QUESTION 4



A maintenance crew needs to enter a manhole containing de-energized
but unverified electrical equipment. What additional step does OSHA
1910.269 require beyond the lockout/tagout procedure?



A) Atmospheric testing every 15 minutes

B) Verification of the de-energized state before entry

C) Continuous ventilation of the manhole

D) A standby employee with a rescue harness



Answer: B



Rationale: OSHA 1910.269 requires that before employees enter manholes
or vaults containing exposed energized electrical equipment, the
equipment must be de-energized AND verification of the de-energized
state must be completed. Verification is a critical safety step that ensures
the equipment is truly de-energized. Option A relates to confined space
requirements but is not the primary requirement for de-energized
equipment. Option C is a general safety consideration but not the specific
OSHA requirement. Option D is a rescue requirement but not the
verification requirement.




QUESTION 5



A distribution engineer is selecting conductors for a new 69 kV
transmission line in a coastal area with high wind loads. According to

, NESC Table 253-1, which factor must be considered when determining the
appropriate conductor loading?



A) The conductor’s color and visual appearance

B) Ice thickness, wind pressure, and temperature

C) The number of spans between structures

D) The conductor’s age and maintenance history



Answer: B



Rationale: NESC Table 253-1 specifies ice and wind load factors based on
NESC loading districts. These factors consider environmental conditions
including ice thickness, wind pressure, and temperature. Option A is
incorrect because conductor color has no bearing on structural loading.
Option C relates to span configuration but not the loading factors specified
in Table 253-1. Option D is a maintenance consideration, not a design
factor for initial loading calculations.




QUESTION 6



A crew is installing a direct-burial 600 V secondary service cable in a
residential area. What is the minimum depth of cover required by the
NEC?



A) 12 inches

B) 18 inches

C) 24 inches

D) 30 inches



Answer: B

Document information

Uploaded on
July 17, 2026
Number of pages
33
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers
$13.49

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
Isabellai
3.5
(6)
Sold
33
Followers
11
Items
1700
Last sold
2 weeks ago


Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions