Written by students who passed Immediately available after payment Read online or as PDF Wrong document? Swap it for free 4.6 TrustPilot
logo-home
Document preview thumbnail
Preview 4 out of 126 pages
Exam (elaborations)

Florida Contractor's Manual Exam | Verified Exam Questions and Answers | Latest Updated Study Material 2026

Document preview thumbnail
Preview 4 out of 126 pages

Florida Contractor's Manual Exam | Verified Exam Questions and Answers | Latest Updated Study Material 2026

Content preview

Florida Contractor's Manual Exam | Verified Exam Questions and
Answers | Latest Updated Study Material 2026

Question:

A Subcontractor's employee incorrectly performs the Work. Who is responsible (to the Owner)
for the error?
1- Subcontractor employee
2- Architect
3- Subcontractor
4- Contractor
Answer:

A201: 3.3.2

Question:

Article 3) Contractor
3.3 Supervision and Construction Procedures
4- Contractor
Which of the following is NOT a cause for the Owner to terminate the Contract?
1- The Contractor experiences delays due to a Stop Work order through an act of government
2- The Contractor fails to make payment to Subcontractors for labor
3- The Contractor is guilty of substantial breach of a provision of the Contract Documents
4- The Contractor repeatedly fails to supply enough properly skilled workers
Answer:

A201: 14.2.1

Question:

Article 14) Termination or Suspension of the Contract
14.2 Termination by the Owner for Cause
1- The Contractor experiences delays due to a Stop Work order through an act of government
Which of the following is owner of all drawings and specifications?
1- Contractor
2- Owner

,3- Architect
4- Supplier
Answer:

A201: 1.5.1

Question:

Article 1) General Provisions
1.5 Ownership and Use of Drawings, Specifications and Other Instruments of Service
3- Architect
Except for those Claims excluded by this AIA A201 Section 15,2,1, an initial decision shall be
required as a condition precedent to mediation of any Claim arising prior to the date final
payment is due, unless 30 days have passed after the Claim has been referred to the Initial
Decision Maker with no decision having been rendered.
1- 10
2- 20
3- 15
4- 30
Answer:

A201: 15.2.1

Question:

Article 15) Claims and Disputes
15.2 Initial Decision
4- 30
The will on request furnish to a information regarding
percentages of completion or amounts applied for by the Contractor
1- Subcontractor; Owner
2- Architect; Subcontractor
3- Owner; Subcontractor
4- Owner; Architect
Answer:

A201: 9.6.3

,Question:

Article 9) Payments and Completiong
9.6 Progress Payments
2- Architect; Subcontractor
To whom is the Subcontractor bound to by the Contract Documents?
1- Architect
2- Owner
3- Themselves
4- Contractor
Answer:

A201: 5.3

Question:

Article 5) Subcontractors
5- 3 Subcontractual Relations
4- Contractor
The Initial Decision Maker will review claims within 10 days of the receipt of the Claim take
one or more of the following actions. Which of the following actions will NOT be taken?
1- Approve the Claim
2- Request additional supporting data from the Claimant
3- Reject the Claim
4- Ignore the request
Answer:

A201: 15.2.2

Question:

Article 15) Claims and Disputes
15.2 Initial Decision
4- Ignore the request
A Sub-subcontractor is a person or entity who has a direct or indirect contract with a/an
to perform a portion of the Work at the site

, 1- Contractor
2- Subcontractor
3- Architect
4- Supplier
Answer:

A201: 5.1.2

Question:

Article 5) Subcontractors
5.1 Definitions
2- Subcontractor
If the Work is stopped for a period of consecutive
days through no fault of the Contractor, or Subcontractor, agents, employees or any other persons
performing portions of the Work under contract with the Contractor, the Contractor may
terminate the Contract and recover from the Owner
1- 120
2- 60
3- 30
4- 45
Answer:

A201: 14.1.4

Question:

Article 14) Termination or Suspension of the Contract
14.1 Termination by the Contractor
2- 60
What is the maximum amount of time after Substantial Completion of the Work shall all claims
(by Owner and Contractor) regarding the Contract by commenced?
1- Six months
2- One year
3- Ten years
4- Five years

Document information

Uploaded on
July 16, 2026
Number of pages
126
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers
$13.49

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Sold
5
Followers
0
Items
4027
Last sold
1 week ago


Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions