Crash - correct answer ✔To shorten an activity or a project
Options when resources are not constrained - correct answer ✔Adding resources, Outsourcing project
work, Scheduling overtime, Establish a core project team, Do it twice - fast and correctly
Options when resources are constrained - correct answer ✔Improve the efficiency of the project
team, Fast tracking, Use critical-chain management, Reduce project scope, Compromise quality
Project cost-duration graph - correct answer ✔A graph that plots project cost against time; it includes
direct, indirect, and total costs for a project over a relevant range of time
Indirect costs - correct answer ✔Costs that cannot be traced to a particular project or work package
Direct costs - correct answer ✔Costs that are clearly charged to a specific work package—usually
labor, materials, or equipment
Crash time - correct answer ✔The shortest time an activity can be completed (assuming a reasonable
level of resources)
Crash point - correct answer ✔The most a project activity time can realistically be compressed with
the resources available to the organization
Management vs Leadership - correct answer ✔Management is about coping with complexity, while
leadership is about coping with change