CON 1200V - Final Exam with Questions and
Answers
Question 1
After the release of the solicitation, you are in involved in an exchange with industry
involving questions about extensions on the due date. According to FAR 15.201,
which of the following guidance is applicable?
Ensure multiple contracting officers can respond to questions as they arise
Ensure that a request for information (RFI) is in place with the required format
Make available to the public any information disclosed to potential offerors as soon
as practicable, but no later than the next general release of information, to avoid an
unfair competitive advantage
None of the above
Correct Answer
Make available to the public any information disclosed to potential offerors as soon
as practicable, but no later than the next general release of information, to avoid an
unfair competitive advantage
Question 2
According to FAR 7.105, a written acquisition plan has two main parts, which are:
Acquisition background and objectives, and plan of action
Competition, and cost
Performance period requirements, and source selection procedures
Risks, and sources
Correct Answer
Acquisition background and objectives, and plan of action
Page 1 of 15
, Question 3
You need to acquire 1,000 machine tools valued at $45,000. How are you required to
publicize your requirement?
The requirement does not need to be publicized because an exception to FAR 5.202
applies for machine tools
The requirement must be publicized electronically through the GPE
Since it is below the SAT and unclassified, notice in a public place will suffice
Since the requirement is an exception to FAR 5.202, it can be posted in a public place
Correct Answer
The requirement must be publicized electronically through the GPE
Question 4
Your RFP has been out for 10 days and you decide that it's in the best interest of the
government to extend the due date for proposals by 15 days. Which of the following
is your correct course of action?
Notify all potential offerors of the change in due date. Be sure to get a delivery
confirmation for the contract file
Cancel the solicitation and issue a new solicitation with the new due date
Amend the solicitation to reflect the new due date
Notify all offerors within the competitive range of the change in due date
Correct Answer
Amend the solicitation to reflect the new due date
Page 2 of 15
Answers
Question 1
After the release of the solicitation, you are in involved in an exchange with industry
involving questions about extensions on the due date. According to FAR 15.201,
which of the following guidance is applicable?
Ensure multiple contracting officers can respond to questions as they arise
Ensure that a request for information (RFI) is in place with the required format
Make available to the public any information disclosed to potential offerors as soon
as practicable, but no later than the next general release of information, to avoid an
unfair competitive advantage
None of the above
Correct Answer
Make available to the public any information disclosed to potential offerors as soon
as practicable, but no later than the next general release of information, to avoid an
unfair competitive advantage
Question 2
According to FAR 7.105, a written acquisition plan has two main parts, which are:
Acquisition background and objectives, and plan of action
Competition, and cost
Performance period requirements, and source selection procedures
Risks, and sources
Correct Answer
Acquisition background and objectives, and plan of action
Page 1 of 15
, Question 3
You need to acquire 1,000 machine tools valued at $45,000. How are you required to
publicize your requirement?
The requirement does not need to be publicized because an exception to FAR 5.202
applies for machine tools
The requirement must be publicized electronically through the GPE
Since it is below the SAT and unclassified, notice in a public place will suffice
Since the requirement is an exception to FAR 5.202, it can be posted in a public place
Correct Answer
The requirement must be publicized electronically through the GPE
Question 4
Your RFP has been out for 10 days and you decide that it's in the best interest of the
government to extend the due date for proposals by 15 days. Which of the following
is your correct course of action?
Notify all potential offerors of the change in due date. Be sure to get a delivery
confirmation for the contract file
Cancel the solicitation and issue a new solicitation with the new due date
Amend the solicitation to reflect the new due date
Notify all offerors within the competitive range of the change in due date
Correct Answer
Amend the solicitation to reflect the new due date