RATED A+
✔✔What are the 2 phases of Progressive DB? - ✔✔- Preliminary Services
- Final Design & Construction
✔✔In _____ DB, the final project cost and schedule commitment is not established as
part of the selection process. - ✔✔progressive
✔✔In _____ DB, the design and price are developed AFTER the design-builder is under
contract. - ✔✔progressive
✔✔In _____ DB, the design-builder is retained by the owner early in the project -
✔✔progressive
✔✔In _____ DB, the design-builder is selected primarily on qualifications -
✔✔progressive
✔✔In Phase 1 (Preliminary services) the design-builder collaborates with the owner to
create or confirm the project's _____ of _____. The _____ advances the design. - ✔✔-
basis of design
- design-builder
✔✔IMPLEMENTING TECHNIQUE No. 2(B): Owners should use a procurement
process that encourages the _______ participation of key _____ _____. - ✔✔- early
- trade contractors
✔✔_____ participation of key trade subcontractors correlates with successful project
delivery - ✔✔Early
, ✔✔In _____ DB, key trade subcontractors are fully integrated into the team. -
✔✔traditional
✔✔In _____ DB, key subcontractors may not be integrated into the team early on, all
depending on the ______ approach. - ✔✔- Progressive
- Owner's
✔✔List 3 options for structuring the DB team? - ✔✔- integrated
- prime-subcontractor relationship
- joint business ventures
✔✔Prime-subcontractor relationships for DB can be led by which entities? - ✔✔-
Contractor-led
- Designer-led
- Developer-led
✔✔DBIA is _____ on how the DB entity should be organized. - ✔✔neutral
✔✔IMPLEMENTING TECHNIQUE: Owners should involve _____ leadership that is
committed to the _____ of the DB process, as this will foster a _____ and _____
relationship among the entire project team. - ✔✔- senior
- success
- healthy
- trusting
✔✔_____ documents prescribe how to achieve the end result. - ✔✔Bridging
✔✔_____ documents describe the end result. - ✔✔Criteria
✔✔DBB Paradigm: Prior to bidding, _____ undertakes a process to design the project,
including all of its details, to ____ complete plans and specs. - ✔✔- Owner
- 100%
✔✔in DBB, the _____ is responsible for success or failure of details of the design and
_____ the sufficiency of design to the _____. - ✔✔- Owner
- warrants
- Contractor
✔✔Owner is liable to contractor for any _____ between plans and specs and Owner's
requirements for project performance. - ✔✔gaps
✔✔In DBB, what is the level of completion at the point of contract. - ✔✔100%