ANSWERS RATED A+
✔✔The _____ project delivery method is well established and understood. - ✔✔DBB
✔✔Which project delivery system is consistent with public sector procurement laws and
the most prevalent delivery system through the 20th century? - ✔✔DBB
✔✔In DBB the _____ _____ is incompatible with expediting project delivery. - ✔✔Linear
sequence
✔✔in _____, the contractor's input is absent during the design process. - ✔✔DBB
✔✔In DBB, the Owner has a "_____ of _____ relationship" with the A/E. - ✔✔Standard
of Care Relationship
✔✔In DBB, the Owner has a "_____ relationship" with the Contractor. - ✔✔Spearing
Relationship
✔✔What 2 methods of selection (procurement methods) does CMAR use? - ✔✔- QBS
- Best Value
✔✔Who provides the pre-construction services for CMAR? - ✔✔Contractor
✔✔What kind of contracting approach is usually used in CMAR? - ✔✔Negotiated GMP
✔✔What is special about the estimating process in CMAR? - ✔✔it is an open-book
✔✔Which delivery methods have the chance to fast track the schedule? - ✔✔- DB
- CMAR
, ✔✔In CMAR, the construction cost is determined _____ the design is completed. -
✔✔before
✔✔In CMAR, the Owner procures and manages designers and contractors under (one /
two separate) contracts? - ✔✔two separate
✔✔In CMAR, the _____ negotiates the full commercial deal. - ✔✔Owner
✔✔In CMAR, what is the direct contractual relationship between the contractor and
designer? - ✔✔There is no direct contractual relationship
✔✔In CMAR, there is _____ public sector authority for its use. - ✔✔limited
✔✔In _____, the owner contracts with one single entity for both design and
construction. - ✔✔DB
✔✔In which project delivery method do the designer and contractor have a direct
contractual relationship? - ✔✔DB
✔✔Which project delivery method has multiple organizational structures? - ✔✔DB
✔✔In DB, How is the Design-Builder generally selected? - ✔✔QBS or Best Value
✔✔Which delivery methods generally uses the selection process of QBS and Best
Value? - ✔✔- DB
- CMAR
✔✔Which delivery method has a wide spectrum of contracting approaches? - ✔✔DB
✔✔The DB system has a(n) _____ _____ of responsibility. - ✔✔Single Point
✔✔In DB, the Owner (does / does not) manage the designer. - ✔✔Does NOT
✔✔What creates innovation potential in DB? - ✔✔Collaboration between the Owner,
Contractor, and Designer
✔✔Which delivery method gives early knowledge of the project cost? - ✔✔DB
✔✔In DB, the Owner's exposure to _____ is significantly reduced. - ✔✔claims
✔✔What is the Single Point of Responsibility Risk? - ✔✔one of the main concerns for
practitioners using DB