What are the elements of Construction Documentation?
Give this one a try later!
Construction drawings and specifications, records of materials and product
investigation and selection, written approval of the documents by the
client, records for bids or proposals, all communications
Addenda is defined as?
Give this one a try later!
Documents issued by the architect to all bidders or proposers that clarify
interpret or modify the bidding or proposal documents before the
contract for construction is signed
,Activity or Task
Give this one a try later!
In scheduling, a basic unit of work as part of the total project that is easily
measured and controlled.
Initial Decision Maker - IDM
Give this one a try later!
For claims between the owner and the contractor is the architect, unless a
third-party is identified.
According to American Institute of Architects (AIA) Documents B101 Standard Form of
Agreement Between Owner and Architect the owner is responsible for providing
what by law?
Give this one a try later!
Testing and inspections
What are the three uses of AIA Contract Documents?
Give this one a try later!
1 Negotiate the terms of your relationship
2 deliver elements of agreement
, 3 Manage risk
What are the seven elements of Bidding or Negotiation? Hint: CAR PIC B
Give this one a try later!
1. C - Records of each prime bidder or negotiating Contractor
2 A - Addenda records
3. R - RFI's and Distribution log
4. P - Pre-bid conference notes,
5. I - record of Insurance
6. C - all Communications
7. B - Bidding Records,
What is one example of contemporaneous documents?
Give this one a try later!
Phone Log
What does B101 Exhibit 1 entails?
Give this one a try later!
, Outlines the responsibilities for each party in order to help mitigate risks
Activities that do not affect the critical path time. To describe the range of time that
noncritical activities can start/end without affecting the overall schedule. iIs consider
____________?
Give this one a try later!
Float
Errors and Omissions
Give this one a try later!
Drawing sets are not a complete set of instructions on how to build the
building, the process of the architect providing clarifications and solving
detail conflicts is an important part of the process to reduce errors.
What will happened if a Critical Activity is delayed?
Give this one a try later!
Give this one a try later!
Construction drawings and specifications, records of materials and product
investigation and selection, written approval of the documents by the
client, records for bids or proposals, all communications
Addenda is defined as?
Give this one a try later!
Documents issued by the architect to all bidders or proposers that clarify
interpret or modify the bidding or proposal documents before the
contract for construction is signed
,Activity or Task
Give this one a try later!
In scheduling, a basic unit of work as part of the total project that is easily
measured and controlled.
Initial Decision Maker - IDM
Give this one a try later!
For claims between the owner and the contractor is the architect, unless a
third-party is identified.
According to American Institute of Architects (AIA) Documents B101 Standard Form of
Agreement Between Owner and Architect the owner is responsible for providing
what by law?
Give this one a try later!
Testing and inspections
What are the three uses of AIA Contract Documents?
Give this one a try later!
1 Negotiate the terms of your relationship
2 deliver elements of agreement
, 3 Manage risk
What are the seven elements of Bidding or Negotiation? Hint: CAR PIC B
Give this one a try later!
1. C - Records of each prime bidder or negotiating Contractor
2 A - Addenda records
3. R - RFI's and Distribution log
4. P - Pre-bid conference notes,
5. I - record of Insurance
6. C - all Communications
7. B - Bidding Records,
What is one example of contemporaneous documents?
Give this one a try later!
Phone Log
What does B101 Exhibit 1 entails?
Give this one a try later!
, Outlines the responsibilities for each party in order to help mitigate risks
Activities that do not affect the critical path time. To describe the range of time that
noncritical activities can start/end without affecting the overall schedule. iIs consider
____________?
Give this one a try later!
Float
Errors and Omissions
Give this one a try later!
Drawing sets are not a complete set of instructions on how to build the
building, the process of the architect providing clarifications and solving
detail conflicts is an important part of the process to reduce errors.
What will happened if a Critical Activity is delayed?
Give this one a try later!