A-Series AIA Contract Documents


Give this one a try later!


Al0l: Standard Form of Agreement Between Owner and Contractor-
Stipulated Sum

A133: Owner-Construction Manager as Constructor Agreement

A195: Owner-Contractor Agreement for Integrated Project Delivery


A201: General Conditions of the Contract for Construction

A295: General Conditions of the Contract for Integrated Project Delivery

A70l: Instructions to Bidders




Program Management (PgM)

,Give this one a try later!


The science and practice of managing large private and public projects.




Assessing the Needs of the Project


Give this one a try later!


Selecting the right delivery method.
Align contract requirements to the project.
Align your own services with the needs of the project.
Identify other parties in the project - based on delivery method (design
build vs design bid build).
Design bid build most prevalent, Const Mgt is second most prevalent.




Uses of AIA Contract Documents (3)


Give this one a try later!


Negotiate the Terms of Your Relationship
Deliver Elements of Agreements
Manage Risks




BIM


Give this one a try later!

, Building Information Modeling




Exhibit-1 to the B101


Give this one a try later!


An initial information exhibit. Used as a checklist. Forms the basis of
Architects / parties understanding of the agreement.

This contract is a standard agreement between the owner and architect. It
outlines the responsibilities for each party in order to help mitigate risk.




What types of Charattes are QM actions in Schematic Design?


Give this one a try later!


Kickoff Charattes, Sustainability Charettes, and Remedial Charettes.




The following is included in an Architect's minimum construction contract
administration services.


Give this one a try later!

, Reporting to the building official
Approving submittals
Reporting to the owner
Shop drawing review
Periodic site visits




Q. A team is assembled to convert a space into a very small veterinary office. The
project is not complex, and the architects estimated that the project fee will be
approximately $30,000. The project requires coordination among the few team
members. Which is the best way to coordinate and manage the project? Select the
best answer.


Give this one a try later!


A. Milestone chart
B. CPM schedule
C. Gantt Chart
D. Bar Chart

Solution: The correct answer is A.
The milestone chart is used for short-duration projects with relatively few
tasks to track and fees under $35,000. It is tempting to use this method for
larger projects, but this would simply not provide the detail needed to
manage the project. A CMP schedule could be another alternative, but in
the case of such a small scope, it is not necessary. The Gantt Chart is the
same as the bar chart.
Reference: Wiley and Sons. (2013). The architect's handbook of professional
practice (15th ed.).




Consequential Damages


Give this one a try later!

Document information

Uploaded on
July 7, 2026
Number of pages
43
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers
$10.50

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
scholarmotivator
4.1
(16)
Sold
148
Followers
48
Items
6079
Last sold
1 week ago



Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions