What is issued when the synchronized reserve is less than the requirement?
A. Voltage Reduction Warning and Reduction of Non-Critical Plant load
B. Manual load Dump Warning
C. VCLC Warning
D. Heavy load Schedule
Give this one a try later!
A. Voltage Reduction Warning and Reduction of Non-Critical Plant load
If PJM experiences a system event that causes the ACE to indicate under generation,
which of the following actions would PJM implement to return tie lines to schedule?
A. Load synchronized reserves
B. Request an IRC
,C. Implement a Heavy Voltage Schedule
D. Request a SSR
Give this one a try later!
A. Load synchronized reserves
If PJM experienced flows that exceeded their Eastern Reactive Interface limit, which
of the following companies generation would be raised to correct the problem?
A. PECO
B. Baltimore Gas & Electric
C. PEPCO
D. Keystone
Give this one a try later!
A. PECO
What is the surge impedance loading on a typical 500kV line?
A. 345 MW
B. 500 MW
C. 850 MW
D. 1050 MW
Give this one a try later!
C. 850 MW
, Which of the following must be completed in order to synchronize if two islands wish
to interconnect during a system restoration event?
A. Loads in the islands must be equal
B. Tie-lines must be established
C. Generation capacity must be within 10% between the islands
D. Phase shifters must be in neutral
Give this one a try later!
B. Tie-lines must be established
When starting an outage on a reportable transmission facility, PJM requires that LCCs
obtain PJM approval prior to removing the facility from service How many minutes
prior to the start of switching must be provided for PJM to study the outage and give
final approval?
A. 15
B. 30
C. 45
D. 60
Give this one a try later!
B. 30
When loads are heavy and bulk power voltage levels are expected to be low PJM will
issue a:
A. Bulk Power Alert
B. Maximum Generation Warning
A. Voltage Reduction Warning and Reduction of Non-Critical Plant load
B. Manual load Dump Warning
C. VCLC Warning
D. Heavy load Schedule
Give this one a try later!
A. Voltage Reduction Warning and Reduction of Non-Critical Plant load
If PJM experiences a system event that causes the ACE to indicate under generation,
which of the following actions would PJM implement to return tie lines to schedule?
A. Load synchronized reserves
B. Request an IRC
,C. Implement a Heavy Voltage Schedule
D. Request a SSR
Give this one a try later!
A. Load synchronized reserves
If PJM experienced flows that exceeded their Eastern Reactive Interface limit, which
of the following companies generation would be raised to correct the problem?
A. PECO
B. Baltimore Gas & Electric
C. PEPCO
D. Keystone
Give this one a try later!
A. PECO
What is the surge impedance loading on a typical 500kV line?
A. 345 MW
B. 500 MW
C. 850 MW
D. 1050 MW
Give this one a try later!
C. 850 MW
, Which of the following must be completed in order to synchronize if two islands wish
to interconnect during a system restoration event?
A. Loads in the islands must be equal
B. Tie-lines must be established
C. Generation capacity must be within 10% between the islands
D. Phase shifters must be in neutral
Give this one a try later!
B. Tie-lines must be established
When starting an outage on a reportable transmission facility, PJM requires that LCCs
obtain PJM approval prior to removing the facility from service How many minutes
prior to the start of switching must be provided for PJM to study the outage and give
final approval?
A. 15
B. 30
C. 45
D. 60
Give this one a try later!
B. 30
When loads are heavy and bulk power voltage levels are expected to be low PJM will
issue a:
A. Bulk Power Alert
B. Maximum Generation Warning