CON 3900 CONTRACTING CURRENTLY
TESTING EXAM 200 QUESTIONS AND
DETAILED VERIFIED ANSWERS WITH
RATIONALES (100% CORRECT ANSWERS
/ALREADY GRADED A+
It addresses FAR and DFARS clauses, contract types (fixed-price, cost-reimbursement, IDIQ,
T&M), socioeconomic programs (8(a), HUBZone, SDVOSB), ethical provisions (OCI, PCI,
Procurement Integrity Act), payment mechanisms, termination procedures, dispute resolution,
and contingency operations. Each question targets a distinct concept including specific dollar
thresholds, statutory requirements, legal doctrines, and documentation mandates. The rationales
provide immediate feedback by explaining the regulatory basis or legal principle behind each
correct answer, making this an effective study tool for DAWIA certification, contracting officer
warrant preparation, and practical contingency contracting knowledge.
1. Who holds the legal authority to obligate government funds in a contingency
contracting environment?
A) Contracting Officer
B) Contracting Officer Representative
C) Administrative Contracting Officer
D) Procuring Contracting Officer
Answer: A
Rationale: Only the warranted Contracting Officer has the delegated authority to
obligate funds; CORs and others lack this authority.
2. What is the minimum consideration required for a valid contract?
1
,A) A written memorandum
B) A promise exchanged for a promise or performance
C) A notarized signatureD) Congressional approval
Answer: B
Rationale: Consideration requires a bargained-for exchange; a promise for a
promise or performance is sufficient.
3. Which type of conflict of interest involves a contractor's ability to bias future
acquisitions due to prior work?
A) Personal conflict of interest
B) Organizational conflict of interest
C) Financial conflict of interest
D) Imputed conflict of interest
Answer: B
Rationale: OCI arises when a contractor's prior work gives it an unfair advantage
or bias in future acquisitions.
4. Which FAR part governs acquisition planning and the development of the
acquisition strategy?
A) FAR Part 1
B) FAR Part 5
C) FAR Part 7
D) FAR Part 15
Answer: C
Rationale: FAR Part 7, Acquisition Planning, covers the development of
acquisition strategies and plans.
2
,5. In a contingency operation, the contracting officer's primary duty is to:
A) Minimize all legal reviews
B) Support the joint force commander's mission through responsive contracting
C) Maximize competition at all costs
D) Defer all decisions to the legal advisor
Answer: B
Rationale: Contingency contracting prioritizes mission support and responsiveness
to operational needs.
6. Which of the following is NOT a required element of a valid contract?
A) Offer
B) Acceptance
C) Sealed bid
D) Consideration
Answer: C
Rationale: A sealed bid is a procurement method, not a required element for
contract formation.
7. The DFARS supplements the FAR for which type of acquisitions?
A) Civilian agency purchases
B) State and local government procurement
C) Department of Defense acquisitions
D) International trade agreements
Answer: C
Rationale: DFARS applies specifically to DoD acquisitions, supplementing the
FAR.
3
, 8. When a contracting officer uses a fixed-price contract, the risk of cost overruns
is primarily borne by:
A) The government
B) The contractor
C) The taxpayer
D) Both equally
Answer: B
Rationale: Fixed-price contracts place maximum cost risk on the contractor.
9. Which document formally notifies a contractor that their proposal has been
accepted?
A) Letter of intent
B) Award notice
C) Memorandum of understanding
D) Request for proposal
Answer: B
Rationale: The award notice formally communicates acceptance of the offer and
creates a binding contract.
10. An unauthorized commitment may be ratified only by:
A) Any government employee
B) The contracting officer
C) The head of the contracting activity
D) The contractor's CEO
Answer: C
4