What is the purpose of the It connects the car body to the tracks.
swing gear on an excavator?
Who is responsible for The Equipment Operator
inspecting a trench before
anyone goes in it?
What is the preferred sling 60 DEGREES
angle?
The top of the spoil pile is Crown
called the?
A four-foot (4) deep trench 25 FEET
requires an additional ladder
for every? open trench.
Materials must be kept back Two feet
from the edge of the trench a
minimum of?
When can an inspector revoke For failure to pay excise tax
a hoisting license?
, Who developed the MA Crane ANSI/ASME
Hand Signals?
DOT stands for? Department of Transportation
When do you do your walk- Before you start it.
around of the equipment?
In the one-to-one sloping Depth or vertical rise.
ratio, what does the 2nd "one"
represent?
On a track machine the gears In the rear
should be where?
When load leveling when do Before you make your lift.
you deploy your stabilizers or
load levelers-before or after
you make the lift?
When backfilling an Small lift "Shade the ditch"
excavation, you should use a?
In the State of Massachusetts The weight of the load exceeds 500 Ibs.
what criteria require a hoisting The height of the load exceeds 10 feet
license? capacity of the bucket exceeds 1/4 cubic
yard
What type of safety system is Lockout-Tagout Total De-energization
used on de-energized system
circuits?
Answers with Verified Solutions | Latest
Updated 2026
What is the purpose of the It connects the car body to the tracks.
swing gear on an excavator?
Who is responsible for The Equipment Operator
inspecting a trench before
anyone goes in it?
What is the preferred sling 60 DEGREES
angle?
The top of the spoil pile is Crown
called the?
A four-foot (4) deep trench 25 FEET
requires an additional ladder
for every? open trench.
Materials must be kept back Two feet
from the edge of the trench a
minimum of?
When can an inspector revoke For failure to pay excise tax
a hoisting license?
, Who developed the MA Crane ANSI/ASME
Hand Signals?
DOT stands for? Department of Transportation
When do you do your walk- Before you start it.
around of the equipment?
In the one-to-one sloping Depth or vertical rise.
ratio, what does the 2nd "one"
represent?
On a track machine the gears In the rear
should be where?
When load leveling when do Before you make your lift.
you deploy your stabilizers or
load levelers-before or after
you make the lift?
When backfilling an Small lift "Shade the ditch"
excavation, you should use a?
In the State of Massachusetts The weight of the load exceeds 500 Ibs.
what criteria require a hoisting The height of the load exceeds 10 feet
license? capacity of the bucket exceeds 1/4 cubic
yard
What type of safety system is Lockout-Tagout Total De-energization
used on de-energized system
circuits?