Question:
1. The critical path on a project can change as the project progresses.
Answer:
True
Question:
2. On a project is a significant event that normally has no duration:,
Answer:
Milestone
Question:
3. The for an activity is the latest possible time an activity might begin without delaying the project
finish date.,
Answer:
Late Start Date
Question:
5. involves the exchange of money for goods and services over electronic networks.
Answer:
E commerce
Question:
6. An online tool designed to facilitate the submission of requests for quotations for a wide range of
commercial products and services is
Answer:
Ebuy
Question:
7. Consumer to consumer C2C ecommerce is the exchange of goods and services between:
,Answer:
Individuals by a third party
Question:
8. are private stores that offer additional customer services beyond simply placing an order.
Answer:
Customer Portals
Question:
9. Cost variance is:
Answer:
the earned value minus the actual cost.
Question:
10. estimate is used for making many purchasing decisions for which accurate estimates are
required and for estimating final project costs.
Answer:
Definitive
Question:
11. Spreadsheets are a common tool for cost estimating, cost budgeting, and cost control.
Answer:
True
Question:
12. If the cost estimate for a project is a basis for contract awards and performance reporting, it
should be a(n) estimate and as accurate as possible.
Answer:
Definitive
Question:
13. are designed to deal with differences in currencies and fluctuating currency exchange rates,
which can cause additional problems in consolidating financial data.
, Answer:
Enterprise Resource System
Question:
14. Which of the following is the objective of customer relationship management CRM software?
Answer:
To capture data about every contact a company has with a customer through every channel and to
store it in the system
Question:
15. Which of the following organizations is a discrete manufacturer?
Answer:
A plane turbine manufacturing company in South Africa
Question:
16. Which of the following provides improved access to quality data for operational decision
making, elimination of costly and inflexible legacy systems, and simplified consolidation of
financial data?
Answer:
An enterprise resource planning system
Question:
17. includes the planning, execution, and control of all activities involved in raw material sourcing
and procurement, conversion of raw materials to finished products, and the warehousing and
delivery of finished products to customers.
Answer:
Supply Chain Management
Question:
18. is a family of data formats that helps people automatically receive feeds anytime there are new
postings to their favorite blog sites, updates in the news headlines, new job listings, or new
information posted at specified Web sites.
Answer:
Really Simple Syndication
Graded A+
Question:
1. The critical path on a project can change as the project progresses.
Answer:
True
Question:
2. On a project is a significant event that normally has no duration:,
Answer:
Milestone
Question:
3. The for an activity is the latest possible time an activity might begin without delaying the project
finish date.,
Answer:
Late Start Date
Question:
5. involves the exchange of money for goods and services over electronic networks.
Answer:
E commerce
Question:
6. An online tool designed to facilitate the submission of requests for quotations for a wide range of
commercial products and services is
Answer:
Ebuy
Question:
7. Consumer to consumer C2C ecommerce is the exchange of goods and services between:
,Answer:
Individuals by a third party
Question:
8. are private stores that offer additional customer services beyond simply placing an order.
Answer:
Customer Portals
Question:
9. Cost variance is:
Answer:
the earned value minus the actual cost.
Question:
10. estimate is used for making many purchasing decisions for which accurate estimates are
required and for estimating final project costs.
Answer:
Definitive
Question:
11. Spreadsheets are a common tool for cost estimating, cost budgeting, and cost control.
Answer:
True
Question:
12. If the cost estimate for a project is a basis for contract awards and performance reporting, it
should be a(n) estimate and as accurate as possible.
Answer:
Definitive
Question:
13. are designed to deal with differences in currencies and fluctuating currency exchange rates,
which can cause additional problems in consolidating financial data.
, Answer:
Enterprise Resource System
Question:
14. Which of the following is the objective of customer relationship management CRM software?
Answer:
To capture data about every contact a company has with a customer through every channel and to
store it in the system
Question:
15. Which of the following organizations is a discrete manufacturer?
Answer:
A plane turbine manufacturing company in South Africa
Question:
16. Which of the following provides improved access to quality data for operational decision
making, elimination of costly and inflexible legacy systems, and simplified consolidation of
financial data?
Answer:
An enterprise resource planning system
Question:
17. includes the planning, execution, and control of all activities involved in raw material sourcing
and procurement, conversion of raw materials to finished products, and the warehousing and
delivery of finished products to customers.
Answer:
Supply Chain Management
Question:
18. is a family of data formats that helps people automatically receive feeds anytime there are new
postings to their favorite blog sites, updates in the news headlines, new job listings, or new
information posted at specified Web sites.
Answer:
Really Simple Syndication