ACTUAL EXAM 2025/2026 QUESTIONS WITH VERIFIED
CORRECT SOLUTIONS || 100% GUARANTEED A PASS NEW
VERSION
A firm begins its strategic business initiative of developing a new business model that will allow
the firm to deliver an efficient, tailored service to its customers. To accomplish this, the firm
initiates a business management project. Which aspect of project management applies to this
firm's project? - answer✔Interdependent Tasks
A firm begins its strategic business initiative of developing a new business model to enhance its
competitiveness. What can be identified as a strategic business initiative for this firm? -
answer✔Improvement in product design
A firm begins a strategic business initiative of developing a new business model that will allow
the firm to deliver an efficient, tailored service to its customers. - answer✔Project sponsor
Which group is included in the five process groups? - answer✔Closing process group
What does PRINCE2 stand for? - answer✔PRojects IN a Controlled Environment
Which PMBOK process group is described as the delivery part of project management where
the main activity happens? - answer✔Executing
Which advantage does the functional (departmentalized) organizational structure provide for a
firm with multiple projects? - answer✔Lines of authority are clear.
,Which two organizations are examples of organizations with the functional organizational
structure? - answer✔(1) The U.S. Department of State and (2) The U.S Department of Energy
An organization expects to use a project management office (PMO) to support multiple projects
that will be implemented within a projectized organizational structure. Which implied effect is a
benefit to this organization? - answer✔Project team members gain access to historical data
from other projects.
Regardless of the organizational structure used to manage a project, an organization elects to
use a project management office (PMO). Which benefit will this organization gain? -
answer✔Projects will coordinate resource usage by monitoring the status of shared resources.
During a certain project phase, specific blueprints are drawn and approved, materials and labor
costs are estimated, prototypes are created, and work activities and tasks are identified. Also,
quality expectations, measurements, and costs are defined. During which project phase do
these activities occur? - answer✔Planning
A project is an operational necessity to repair a design flaw in the date field that constrains the
year number to two digits, instead of permitting the year to be indicated with four digits. If the
project is not completed before December 31, 1999, many legacy programs are expected to fail
or produce unpredictable outcomes. The marketing department wants to upgrade its existing
computer equipment and have the costs included in the budget for this project. The project
team implemented the marketing department's request without completing the formal change
control procedures.
What has happened to the scope baseline in this scenario? - answer✔Scope creep has caused a
scope variance.
A general contractor is managing a highway construction project that will repair a flood-
damaged road. The project was documented in a cost-plus-incentive fee contract that specified
a completion date of June 30. The Department of Transportation has offered an incentive for
early completion of the repairs.
,Which triple-constraint baseline remains unchanged by the effects of the incentive? -
answer✔Scope
In Project A, the contract specifies that time is very important. All of the scope must be
completed, or the project will fail. The project's objective requires the project team to work as
quickly as possible.
Which triple constraint can be adjusted to permit the project team to work as quickly as
possible? - answer✔Cost
In Project B, all of the scope must be completed, or the project will fail. The work is important
but not urgent.
Which triple constraint can be adjusted if the project's objective requires the project team to
work at the lowest possible cost? - answer✔Time
A project manager is discussing the latest financial reports of a project to construct a grocery
store and is approximately 90% into the planning phase. The project manager has been told by a
project team member that other grocery stores in the area have an automated teller machine
(ATM) for visitors. An ATM has not been discussed or incorporated into the planning of this
project nor have any been incorporated into prior grocery store services. The leader calls for the
immediate addition of an ATM into all prior grocery stores.
Which non-numeric model is this leader using? - answer✔Competitive necessity
An organization has a surplus of project dollars in the operating budget. The senior leader's
decision is to fund one more project with the remaining funds. Of the three projects proposed,
one of the projects was selected without evaluation of feasibility or viability.
Which non-numeric model is this leader using? - answer✔Sacred cow
, Each project team member generated a series of questions to evaluate three projects. The
checklist was compiled into one list based on frequency of question content, such as personnel,
materials, experience, and time. The more frequent the question content, the more likely the
questions would be asked first.
Which two benefits result from this checklist approach? - answer✔(1) Operational impact has
been built in (2) Strategic impact has been integrated.
Each project team member generated a series of questions to evaluate three projects. A
checklist was then compiled into one list based on the frequency of question content, such as
personnel, materials, experience, and time.
Place the project activities in order of occurrence from first (1) to last (5). - answer✔(1)
Collecting customer requirements (2) Developing the work breakdown structure (3) Working to
produce project deliverables (4) Customers evaluating the project outcomes (5) Capturing
lessons learned
During which life cycle phase is the vast majority of the actual work to produce the project's
deliverables completed? - answer✔Executing
What is the correct term for an intermediate outcome of project work, such as a signed contract
or obtaining a construction permit? - answer✔Deliverable
Which deliverable from a work breakdown structure (WBS) is not specific enough to measure its
completion at project closure? - answer✔User training
The following table shows the Level 1 work breakdown structure (WBS) for Project A.