Question 1: According to DBIA's "Design-Build Done Right" principles, what is the
primary purpose of the "Partnering" or "Big Room" concept during project
execution?
A. To provide a large, shared workspace to reduce office rental costs for the design-
builder.
B. To enable co-location of the integrated team to foster collaboration, rapid
communication, and proactive problem-solving.
C. To establish a physical location for the owner's project manager to oversee the
contractor's daily work.
D. To create a formal meeting space for dispute resolution and claims negotiation.
CORRECT ANSWER: B. To enable co-location of the integrated team to foster
collaboration, rapid communication, and proactive problem-solving.
Rationale: The "Big Room" or co-location is a key "Design-Build Done Right" strategy. It
brings the entire integrated project team together in a shared physical space to break
down silos, facilitate real-time communication, and promote a collaborative culture.
This environment supports early issue identification and resolution, enhancing overall
project efficiency and outcomes .
Question 2: In the context of DBIA best practices for procurement, what is an
"Alternative Technical Concept" (ATC)?
A. A low-cost alternative material substitution proposed during construction.
B. A high-risk, high-reward technical innovation offered after the contract is awarded.
C. A cost-saving or value-adding proposal presented by a proposer that deviates from
the RFP's base requirements during the procurement phase.
D. A mandatory sustainability requirement that all proposers must include in their base
bid.
CORRECT ANSWER: C. A cost-saving or value-adding proposal presented by a
proposer that deviates from the RFP's base requirements during the procurement
phase.
Rationale: An Alternative Technical Concept (ATC) is a mechanism in the procurement
phase allowing proposers to offer innovations that differ from the RFP's stated
requirements. This process encourages innovation and can lead to better value for the
owner. ATCs are typically vetted with the owner during proprietary meetings before final
proposals are submitted .
,Question 3: The DBIA certification exam covers a broad spectrum of knowledge
domains. Which of the following is a primary topic tested on the exam?
A. Advanced Structural Engineering Calculations
B. Human Resources and Labor Law
C. Procuring Design-Build Services
D. Corporate Financial Accounting
CORRECT ANSWER: C. Procuring Design-Build Services.
Rationale: The DBIA Certification Exam is structured to measure mastery of design-
build best practices. The exam domains include "Procuring Design-Build Services"
which accounts for a significant portion of the test, alongside other topics like "Guiding
Principles," "Contracting," and "Executing Design-Build Projects" .
Question 4: What is the primary legal characteristic of a "Teaming Agreement" in a
Design-Build pursuit?
A. It is the final contract between the owner and the design-builder.
B. It is a legally binding contract between the lead contractor and lead designer that
establishes their relationship and obligations before the owner's contract is awarded.
C. It is a non-binding memorandum of understanding that can be broken without
consequence.
D. It is a legal document that transfers all project risk from the design-builder to the lead
designer.
CORRECT ANSWER: B. It is a legally binding contract between the lead contractor
and lead designer that establishes their relationship and obligations before the
owner's contract is awarded.
Rationale: A Teaming Agreement is a critical document executed between the prime
contractor and the lead design firm before they submit a proposal. It legally defines
their roles, responsibilities, intellectual property rights, and cost-sharing arrangements,
providing a crucial framework for collaboration during the high-stakes proposal phase
and beyond .
Question 5: In the context of DBIA Standard Form agreements, what is the primary
purpose of a "Confirmatory Payment" or "Honorarium"?
A. To pay the winning proposer's full fee upon contract signing.
B. To reimburse unsuccessful shortlisted proposers for the cost of preparing their
proposals.
C. To pay the owner's advisor for their services during the procurement process.
D. To provide an upfront payment to the design-builder for early procurement of long-
lead materials.
CORRECT ANSWER: B. To reimburse unsuccessful shortlisted proposers for the
cost of preparing their proposals.
,Rationale: An honorarium (or stipend) is provided to unsuccessful shortlisted proposers
to offset their proposal preparation costs. This practice encourages robust competition,
recognizes the significant intellectual property and effort invested by proposing teams,
and maintains goodwill, which is a key "Design-Build Done Right" strategy .
Question 6: What is the strategic advantage of using a Two-Phase Selection
process for a design-build project?
A. It guarantees the lowest possible price by encouraging maximum competition.
B. It allows the owner to select a team based on qualifications before expensive,
detailed proposals are developed.
C. It significantly reduces the overall project schedule by allowing construction to start
immediately.
D. It allows the owner to negotiate with all proposers simultaneously to drive prices
down.
CORRECT ANSWER: B. It allows the owner to select a team based on qualifications
before expensive, detailed proposals are developed.
Rationale: Two-Phase Selection is used to pre-qualify the most highly qualified teams
based on their experience and approach (Phase 1) before requesting a detailed
technical and price proposal (Phase 2). This method reduces the cost of competition
and focuses the effort on the best-suited teams, which is particularly beneficial for
complex projects where qualifications are paramount .
Question 7: In a Design-Build project, who is typically responsible for obtaining the
building permit?
A. The Owner
B. The Design-Builder
C. The Owner's Representative
D. The Lead Architect
CORRECT ANSWER: B. The Design-Builder.
Rationale: As the single point of responsibility, the Design-Builder manages the
permitting process. This integrated approach streamlines approvals and ensures that
design and construction documents comply with local codes and regulations, a key
benefit of the design-build delivery method .
Question 8: Which insurance policy is specifically designed to cover the Design-
Builder for errors and omissions in the design?
A. General Liability (GL)
B. Workers' Compensation
C. Professional Liability (PL) / Errors and Omissions (E&O)
D. Builder's Risk
CORRECT ANSWER: C. Professional Liability (PL) / Errors and Omissions (E&O).
, Rationale: Professional Liability insurance, also known as Errors and Omissions (E&O),
covers claims related to professional negligence or inadequate work performed by
architects, engineers, and other design professionals. Since General Liability policies
typically exclude professional services, this coverage is essential for a Design-Builder
who is responsible for both design and construction .
Question 9: What is the primary responsibility of an "Owner's Advisor" or
consultant on a design-build project?
A. To take over the Design-Builder's responsibilities if they fail to perform.
B. To serve as the Architect of Record and sign off on all design documents.
C. To assist the owner in developing the RFQ/RFP and monitoring the design-builder's
compliance with the contract requirements.
D. To manage the construction site and directly supervise the Design-Builder's crews.
CORRECT ANSWER: C. To assist the owner in developing the RFQ/RFP and
monitoring the design-builder's compliance with the contract requirements.
Rationale: Many owners hire an advisor or consultant with expertise in design-build to
help navigate the complexities of procurement and project delivery. This advisor assists
in developing clear RFQ/RFP documents and oversees the project on the owner's behalf
to ensure the Design-Builder meets the established criteria and contract obligations .
Question 10: According to DBIA best practices, when should a teaming agreement
ideally be executed?
A. After the contract is awarded to the team.
B. Before any significant work is performed on the proposal.
C. Only if the owner requires it in the RFP.
D. During the construction phase.
CORRECT ANSWER: B. Before any significant work is performed on the proposal.
Rationale: A teaming agreement should be executed early in the pursuit phase, before
significant proposal development work begins. This early execution is crucial to prevent
disputes regarding the division of costs, roles, responsibilities, and intellectual property
rights during the high-pressure and expensive proposal development period .
Question 11: How does the "Spearin Doctrine" typically apply in a Design-Build
context compared to Design-Bid-Build?
A. It is irrelevant because the owner always warrants the plans in both methods.
B. It is significantly limited because the Design-Builder is responsible for creating the
plans they are following, thus the owner does not warrant the design.
C. It provides more protection for the Design-Builder against owner-caused delays.
D. It is legally prohibited from being included in any design-build contract.