Questions and Correct Answers
Question 1
When should you create a change event?
Correct Answer
Once you create a change order
Question 2
What does the "Forecast to Complete" column show?
Correct Answer
The difference between the projected budget and what you expect the total cost of
completion to be at the end of the project
Question 3
True or False: Daily Log entries can be entered for a future date.
Correct Answer
true
Question 4
True or False: When you link an RFI to a drawing, you will see the drawing linked on
the RFI's view page.
Correct Answer
true
Page 1 of 37
,Question 5
True or False: A Budget Modification allows you to move budgeted costs to different
line items.
Correct Answer
true
Question 6
True or False: When you delete a specification from the Specifications list page, you
will delete the specification and all of its revisions.
Correct Answer
True
Question 7
True or False: Observations can only be created using an observation template.
Correct Answer
false
Question 8
Why are some action buttons inactive and gray?
Correct Answer
Because certain actions require that you first select one or more spec sections
before the button becomes active and orange (i.e. clickable)
Question 9
True or False: When you save a submittal as a draft, no notifications are sent out to
the members of the distribution list and workflow.
Correct Answer
true
Page 2 of 37
,Question 10
True or False: Company level inspection templates must be added to a project before
any new inspections can be performed for that project.
Correct Answer
true
Question 11
What is the RFI Manager?
Correct Answer
A user who will receive notification emails when the RFI is responded to or updated
Question 12
Which of the following is a toolbar option in the Models tool?
Correct Answer
All of the above
Question 13
What is the best way to inform bidders of a change to the bid documents after they
have been sent out?
Correct Answer
Procore will automatically notify bidders of a change to bid documents
Question 14
True or False: Punch List templates are only available for use on Procore's mobile
application.
Correct Answer
false
Page 3 of 37
, Question 15
Who can view drawing markups on your 'Personal' layer?
Correct Answer
Only you
Question 16
Which of the following can you do when viewing a drawing on a mobile device?
Correct Answer
B and C
Question 17
What is the best way to be notified of changes made to a file or folder?
Correct Answer
Use the built-in file tracking feature
Question 18
True or False: You can create a commitment directly from an awarded bid
Correct Answer
true
Question 19
What are the best practices you should communicate to the Design Team about the
formatting of the spec book?
Correct Answer
All of the above