Management Exam question with correct
answers (100% verified answers) plus
rationales Q &A
2026 INSTANT DOWNLOAD PDF
1. What is the primary objective of project management in biotechnology?
A. Increase laboratory size
B. Ensure regulatory compliance only
C. Deliver biotech projects within scope, time, and cost
D. Replace scientific research
Answer: C
Rationale: Biotechnology project management focuses on delivering projects
efficiently within defined scope, time, cost, and quality constraints.
2. Which phase comes first in the biotech project lifecycle?
A. Execution
B. Initiation
C. Monitoring
D. Closure
Answer: B
Rationale: Initiation defines the project and its feasibility before planning and
execution begin.
,3. What document formally authorizes a project?
A. Risk register
B. Project charter
C. Gantt chart
D. SOP manual
Answer: B
Rationale: The project charter formally authorizes the project and defines
objectives and stakeholders.
4. In biotech projects, regulatory compliance is primarily associated with:
A. Marketing
B. FDA guidelines
C. HR policies
D. Financial auditing
Answer: B
Rationale: Biotechnology projects must comply with FDA and other regulatory
authorities.
5. Which tool is best for scheduling biotech project tasks?
A. SWOT analysis
B. Gantt chart
C. Fishbone diagram
D. Pareto chart
Answer: B
Rationale: Gantt charts visually represent timelines and task dependencies.
,6. What is a critical path in project management?
A. Least expensive tasks
B. Longest sequence of dependent tasks
C. Optional activities
D. Risk-free tasks
Answer: B
Rationale: The critical path determines the shortest possible project duration.
7. What does GMP stand for in biotechnology?
A. General Manufacturing Policy
B. Good Manufacturing Practice
C. Genetic Mapping Procedure
D. Global Medical Protocol
Answer: B
Rationale: GMP ensures products are consistently produced and controlled
according to quality standards.
8. What is the main purpose of risk management in biotech projects?
A. Increase profits
B. Identify and mitigate uncertainties
C. Hire employees
D. Replace QA teams
Answer: B
Rationale: Risk management reduces uncertainty and improves project success.
9. Which is NOT a stakeholder in biotech projects?
, A. Regulatory agency
B. Project manager
C. Random public observer
D. Laboratory scientist
Answer: C
Rationale: Only individuals or groups directly affected or involved are stakeholders.
10. What does FDA primarily regulate?
A. Education
B. Food and drug safety
C. Transportation
D. Banking
Answer: B
Rationale: FDA regulates food, drugs, biologics, and medical devices.
11. What is the purpose of a Work Breakdown Structure (WBS)?
A. Increase project cost
B. Divide project into manageable tasks
C. Eliminate stakeholders
D. Replace documentation
Answer: B
Rationale: WBS breaks down work into smaller, manageable components.
12. In biotech, validation ensures:
A. Marketing success
B. Equipment and processes meet intended use
C. Employee satisfaction
D. Budget reduction