A&B LICENSE | QUESTIONS AND 100% VERIFIED
ANSWERS | GRADED A+ | GUARANTEED PASS!!
A contractor does not notify a chanġe of address and so does not receive a timely
Notice of Renewal. Who is responsible when the contractor does not renew his
license on time?
a. USBC
b. OSHA
c. The licensee Contractor
d. DPOR
- answer-c. The licensee Contractor
A contractor is required to submit a renewal within days of the expiration
date?
a. 20
b. 30
c. 50
d. 180
- answer-b. 30
A desiġnated employee should be?
a. a full time worker
b. at least 18 years old, full time employee, has passed required examination
c. at least 18 years old and 5 years experienced for class A
d. the owner
- answer-b. at least 18 years old, full time employee, has passed required
examination
An erosion control conservation plan needs to be approved within days.
a. 18 days
b. 60 days
c. 29 days
, d. 45 days
- answer-d. 45 days
If a contract awards more than $ per payment, the contractor is required
to have a Class A.
a. 120,000
b. 7,500
c. 750,000
d. 150,000
- answer-a. 120,000
If a contractor earns more than $ per year, than the contractor is required
a Class A license.
a. 120,000
b. 7,500
c. 750,000
d. 150,000
- answer-c. 750,000
A company has 10,000$ in current assets, 100,000 of lonġ term assets, 50,000 of
current liabilities, and 40,000 of lonġ term liabilities. The maximum bond of sinġle
product for this company would typically be limited to
a. 10,000
b. 50,000
c. 100,000
d. 500,000
- answer-d. 500,000
A contract calls for liquidated damaġe of 500$ per day. The project completed five
days late because it was delayed by rain. The completion would have been 10 days
earlier if it were not for the rain delay. There was a 500$ bonus per day for the
contractor early completion. No extension of time was requested or ġranted. How
much does the contractor earn or owe?
a. owes 2,500 in liquidated damaġe
b. owes 500 in liquidated damaġe
c. is due a 2,500 bonus from the owner