What is included within the statement of work for the supplier?
a) The identification of managing responsibilities
b) The identification of relevant processes to be followed
c) The budgeted cost of the work performed
d) The identification of some tasks to be performed - correct answer b) The
identification of relevant processes to be followed
Which components are included within the outsourcing agreement?
a) Contract, statement of work, and technical specs
b) Contract, selection, and technology used
c) Contract, negotiations, and technical specs
d) Contract, selection, and subcontract management - correct answer a) Contract,
statement of work, and technical specs
,Which factor could positively impact a project's performance the most if it is prioritized
while a supplier is being selected?
a) Selecting the supplier based on around-the-clock geographic location
b) Selecting the supplier based on the lowest price cost
c) Selecting the supplier based on its prior performance on similar work
d) Selecting the supplier based on the available staff - correct answer a) Selecting the
supplier based on around-the-clock geographic location
What is the correct order of steps in risk management?
a) Approach and fix risks; develop future risk plans; implement risk mitigation plans
b) Identify and analyze risks; develop risk mitigation plans; implement risk mitigation
plans
c) Implement the risks; develop risk plans; identify and analyze risks
,d) Develop risk mitigation plans; identify and analyze risks; implement risk mitigation
plans - correct answer b) Identify and analyze risks; develop risk mitigation plans;
implement risk mitigation plans
n terms of what we have covered for risks, which particular formula does risk
management refer to?
a) RE = P(event) X consequences
b) RE = P(consequences) X event
c) ER = P(consequences) / event
d) ER = P(event) + consequences - correct answer a) RE = P(event) X consequences
Suppose you work at a software company and newer members have been added
globally. You are working on an important project and need a coworker who works in
India to help you modify and improve your software. You try to reach him but he is not
in office and you leave a note. Your coworker also has trouble with English and
assumes what he has read. Instead, your coworker starts running unit testing on the
, software and discovers many problems. What challenge to global software
development does this relate to?
a) Inadequate global management
b) Lack of shared values and strategies
c) Insufficient communication
d) Cultural differences - correct answer c) Insufficient communication
Which of the following cultures refers to "focussing on one thing at a time"
a) Low context culture
b) Monochronic culture
c) Polychronic culture
d) High context culture - correct answer b) Monochronic culture
Which of the following factors positively influences the adoption of agile development
in large scale global software development?