Exam 2 (Latest Update )
Questions with Correct Answers {Grade
A}100% Verified
What factors are considered part of tracking and oversight activities? - correct answer
Visibility, performance metrics, and risk management
What does a manager need to know in order to manage distributed teams? - correct
answer How to build teams across sites
What is considered a high risk in distributed teams? - correct answer Team members
do not share a common language and have different communication norms.
In which step of risk management should we prioritize risks? - correct answer Identify
and analyze risks
Suppose you work at a software company and newer members have been added
globally. You are working on an important project and need a coworker who works in
,India to help you modify and improve your software. You try to reach him but he is not
in office and you leave a note. Your coworker also has trouble with English and
assumes what he has read .Instead, your coworker starts running unit testing on the
software and discovers many problems. What challenge to global software
development does this relate to? - correct answer Insufficient communication
Which of the following cultures refers to "communicate implicitly and rely heavily on
context"? - correct answer High context culture
Which of the following can be considered as external factors in SWOT framework for
scaling agile development ? - correct answer regular customer feedback
Which of the following is a strategy for deciding which activities should be
subcontracted? - correct answer Maximize the organization's effectiveness
Which process does the software leader make sure is being followed before
commencing to any process improvement? - correct answer Actual Process
,The Perceived Process: - correct answer What you think you do
The Official Process: - correct answer What you are supposed to do
The Actual Process: - correct answer What you do
In characterizing the current process, which process deals with what you are
supposed to do? - correct answer The official process
When analyzing the current process, what is a major goal of the analysis? - correct
answer To identify sources of variation in the process and value-added and non-value-
added activities.
How broadly can root cause analysis be applied based on defects? - correct answer
Defects introduced by all development activities
Defects: - correct answer Any flaw in the product
, Cause: - correct answer The underlying process flaws associated with the defect
What kind of reasoning process is root cause anaylsis? - correct answer Group
reasoning
What is the worst time to perform root cause analaysis? - correct answer At the
beginning of a project
In terms of root cause analysis, what is the difference between a defect and a cause? -
correct answer A defect is a flaw in a product whereas a cause is the underlying
process flaws associated with the defect.
What is a given cost of utilizing root cause analysis? - correct answer Time to facilitate
process
What is the correct order for the process improvement phases? - correct answer
Characterize the current process, analyze the current process, characterize the target
process, process redesign, implementation