CAL FIRE Weekly Fire Pump Certification Exam – Real-Style Exam Questions | 100% Correct Answers | Pump Operations | Drafting Procedures | Pressure Calculations | Maintenance Checks | OSFM Standards | Detailed Rationales | Graded A+ Verified – Pass Guaranteed – Instant Download

Show more Read less
Institution
Cal Fire
Course
Cal Fire

Content preview

CAL FIRE Weekly Fire Pump Certification Exam OSFM –
Complete Exam-Style Questions with Detailed Rationales |
100% Verified – Pass Guaranteed – A+ Graded


Question 1
Per NFPA 25 (2023/2026 Edition), what is the minimum required run time for a weekly
no-flow (churn) test of a diesel engine-driven fire pump?

A. 10 minutes
B. 20 minutes
C. 30 minutes
D. 60 minutes

Correct Answer: C
Rationale: NFPA 25 Section 8.3.1 requires diesel engine-driven fire pumps to run for a
minimum of 30 minutes during weekly no-flow (churn) tests. Electric motor-driven
pumps require a minimum of 10 minutes. Option A (10 minutes) applies to electric
pumps, not diesel. Option B (20 minutes) has no basis in the standard. Option D (60
minutes) exceeds the minimum requirement and is not mandated by NFPA 25 for
weekly testing.



Question 2
A CAL FIRE station in rural Shasta County operates a diesel-driven fire pump. During the
weekly churn test, the pump starts automatically but takes 25 seconds to reach rated
speed. What action is required per NFPA 20 and NFPA 25?

A. No action is required; 25 seconds is within normal limits
B. Document the finding and continue testing; investigate if the condition worsens
C. Shut down the pump immediately and tag it out of service
D. Increase the fuel supply to improve acceleration

,Correct Answer: B
Rationale: NFPA 20 requires diesel engines to reach rated speed within 20 seconds of
the automatic start signal. While 25 seconds exceeds this threshold, NFPA 25 does not
mandate immediate system shutdown for a minor deviation during a weekly test. The
correct procedure is to document the finding, continue the test, and investigate the
cause (potentially weak batteries, fuel issues, or governor problems) before the next
test. Option A is incorrect because 25 seconds exceeds the 20-second requirement.
Option C is excessive for a weekly test finding unless the pump fails to start entirely.
Option D is unsafe and could cause engine damage or overspeed.



Question 3
During a weekly fire pump test at a Sacramento school campus, the technician observes
that the packing gland on a horizontal split-case pump is completely dry with no visible
leakage. What is the most appropriate action?

A. Tighten the gland nuts until a slight drip appears
B. Replace the packing immediately
C. Loosen the gland nuts to allow a slight discharge of approximately one drip per
second
D. Report the pump as inoperable and shut down the system

Correct Answer: C
Rationale: NFPA 25 requires pump packing glands to show a slight discharge
(approximately one drip per second) during operation to prevent overheating and shaft
damage. A completely dry gland indicates over-tightening, which will cause excessive
friction, scoring of the shaft sleeve, and premature failure. Option A would worsen the
over-tightening condition. Option B is unnecessary if the packing is not worn out—only
the gland nut adjustment is needed. Option D is excessive; the pump is not inoperable
but requires immediate gland adjustment.

,Question 4
Under California CCR Title 19, Section 905, who is authorized to perform weekly fire
pump tests in structures owned or leased by a public entity?

A. Any maintenance employee of the public entity
B. Only a C-16 licensed fire protection contractor
C. An individual holding a California State Fire Marshal Weekly Fire Pump Test
Certificate employed by a Licensed A (Type L) Concern
D. Any NICET-certified technician regardless of California licensure

Correct Answer: C
Rationale: CCR Title 19, Section 905(l)(2) requires every person who performs weekly
fire pump tests within the limitations of a Type L license to pass a written examination
and hold a California State Fire Marshal Weekly Fire Pump Test Certificate. The
individual must be employed by a Licensed A (Type L) Concern. Option A is incorrect
because untrained employees are not authorized. Option B is incorrect because while
C-16 contractors can perform these tests, public entities may use their own Type
L-licensed personnel with the proper certificate. Option D is incorrect because NICET
certification alone does not satisfy California's specific OSFM certificate requirement.



Question 5
During a weekly churn test of an electric fire pump in a San Francisco high-rise building,
the discharge pressure gauge reads 142 psi while the suction pressure reads 8 psi. The
pump nameplate indicates a rated pressure of 150 psi. What does NFPA 25 require?

A. The test is satisfactory; no further action is needed
B. The pressure difference (134 psi) must be investigated because it is less than 95% of
rated pressure
C. The pressure difference (134 psi) exceeds 95% of rated pressure and must be
investigated and corrected
D. Replace the discharge pressure gauge immediately

Correct Answer: C

, Rationale: NFPA 25 Section 8.3.1.2 requires investigation and correction when the
recorded pressure difference between discharge and suction gauges is greater than
95% of the rated pump pressure. Here, 95% of 150 psi = 142.5 psi. The actual net
pressure is 134 psi (142 - 8), which is less than 95% of rated (142.5 psi). Wait—let me
recalculate: The question states discharge is 142 psi, suction is 8 psi, so net pressure is
134 psi. 95% of 150 psi = 142.5 psi. Since 134 psi is LESS than 142.5 psi, this indicates
a performance deficiency that requires investigation. The standard requires
investigation when the difference is greater than 95%—meaning if the net pressure
exceeds 142.5 psi, that's acceptable; if it's below, it requires investigation. Actually,
re-reading: "Where the recorded pressure readings on the discharge and suction gauges
show a difference that is greater than 95 percent of the rated pump pressure"—this
means if net pressure > 95% of rated, it's acceptable. If net pressure < 95% of rated,
investigation is required. Since 134 psi < 142.5 psi, investigation is required. Option C
correctly identifies that the difference must be investigated. Option A is incorrect
because the net pressure is below the 95% threshold. Option B incorrectly states the
pressure difference is less than 95% as the reason—actually the net pressure IS less
than 95%, which triggers investigation. Option D is premature; gauge calibration should
be verified first.



Question 6
A fire pump controller at an industrial facility in Los Angeles uses a pressure-actuated
start circuit. During the weekly test, the technician uses the manual "START" button on
the controller front panel to initiate the churn test. What is wrong with this procedure per
NFPA 25?

A. Nothing; manual start is an acceptable alternative to automatic start
B. The pump must be started by creating a pressure drop in the sensing line to simulate
actual system demand
C. The jockey pump must be running before the main pump can be started

Written for

Institution
Cal Fire
Course
Cal Fire

Document information

Uploaded on
June 12, 2026
Number of pages
32
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

$16.00
Get access to the full document:

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
PrimeScholars Rasmussen college
View profile
Follow You need to be logged in order to follow users or courses
Sold
62
Member since
1 year
Number of followers
0
Documents
3010
Last sold
5 hours ago
ExamPrep Hub

ExamPrep Hub delivers premium expertly curated exam materials designed for serious students who aim for top performance. our resources are structured for clarity, accuracy, and efficiency helping you master concept, revise smarter and achieve outstanding result

3.2

10 reviews

5
4
4
0
3
3
2
0
1
3

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions