THE __________ IS RESPONSIBLE TO MAINTAIN SPRINKLER SYS. AND TO DETERMINE QUALIFICATIONS.
OWNER
RECORDS OF ALL INSPECTIONS AND MX SHALL BE MAINTAINED ON PREMISES FOR A MIN. OF
__________ YEARS.
3
THE BUILDING OWNER SHALL ASSIGN A(N) ____________ TO COMPLY WITH REQUIREMENTS.
IMPAIRMENT COORDINATOR
REGULAR MX AND MINOR REPAIRS NOT AFFECTING MORE THAN ________ FLOOR(S) ARE CONSIDERED
PLANNED REMOVAL FROM SERVICE.
1
SHUTDOWNS AFFECTING MORE THAN _________ FLOOR(S) ARE CONSIDERED UNPLANNED OUT OF
SERVICE CONDITIONS.
1
6/8/2026
1
, S-12 CITYWIDE SPRINKLER SYSTEMS, S12 SPRINKLER TEST
06/08/2026
EXAM QUESTIONS AND ANSWERS
NOTIFICATION TO FDNY IS NOT REQUIRED, PROVIDED SYSTEM IS RETURNED TO SERVICE WITHIN ______
HOURS.
8
FOR UNPLANNED REMOVAL FROM SERVICE, THE COF HOLDER SHALL IMMEDIATELY REPORT CONDITION
TO THE ___________ AND THE FIRE DEPT.
OWNER OF THE BUILDING
IF A MINOR DEFECT IS OBSERVED, IT SHALL BE CORRECTED WITHIN _________ DAYS OR IT WILL BE
CONSIDERED AN IMPAIRMENT.
30
WHAT DOES "OOS" STAND FOR?
OUT OF SERVICE
OOS SYSTEMS SHALL BE IDENTIFIED BY PLACING ________ AT FIRE DEPT. CONNECTIONS, SYS. CONTROL
VALVES, AND FIRE COMMAND CENTER
TAGS
A _______ SHALL BE REQUIRED TO POST TAGS AT MAIN CONTROL VALVE AND ANY SECTIONAL VALVES.
MASTER FIRE SUPPRESSION PIPING CONTRACTOR
6/8/2026
__________ SHALL BE POSTED ON THE TAG INDICATING BOTH STATIC AND FLOW PRESSURES BEFORE
AND AFTER.
2
, S-12 CITYWIDE SPRINKLER SYSTEMS, S12 SPRINKLER TEST
06/08/2026
EXAM QUESTIONS AND ANSWERS
DRAIN TEST RESULTS
GREEN TAGS INDICATE THAT __________.
NO IMPAIRMENT WAS FOUND
GREEN TAGS WILL BE PLACED ON THE ____________.
MAIN CONTROL VALVE
SYSTEMS PARTIALLY OR FULLY OUT OF SERVICE SHALL HAVE A ____________ TAG PLACED ON THE
MAIN CONTROL VALVE.
RED
A _________ DISC OF 8-9 INCHES SHALL BE PLACED ON CONNECTIONS TO INDICATE THE SYSTEM IS
FULLY OUT OF SERVICE.
WHITE
A ________ DISC OF 8-9 INCHES SHALL BE PLACED ON CONNECTIONS TO INDICATE THE SYSTEM IS
PARTIALLY OUT OF SERVICE.
BLUE
THE IMPAIRMENT COORDINATOR WILL NOTIFY THE ___________ CARRIER, CENTRAL STATION AND
OCCUPANTS.
6/8/2026
INSURANCE
3
, S-12 CITYWIDE SPRINKLER SYSTEMS, S12 SPRINKLER TEST
06/08/2026
EXAM QUESTIONS AND ANSWERS
PRIOR TO RETURNING A SYS. TO SERVICE, THE ___________ SHALL ENSURE THAT NECESSARY TESTS
AND INSPECTIONS ARE CONDUCTED.
IMPAIRMENT COORDINATOR
GLYCERIN NOT GREATER THAN _________ PERCENT OR GLYCOL NOT GREATHER THAN ________
PERCENT SHALL BE USED TO PROTECT FROM FREEZING.
50, 40
THE COF NUMBER AND SIGNATURE OF COF HOLDER SHALL BE POSTED NEAR THE ____________.
MAIN CONTROL VALVE
__________ SHALL BE READILY AVAILABLE TO ANY REPRESENTATIVE OF THE FIRE DEPT. THESE ARE TO
BE MAINTAINED ON SITE FOR 3 YEARS.
RECORDS
FAILURE TO MAKE INSPECTIONS MAY RESULT IN __________ OF THE COF AND COURT PROCEEDINGS.
REVOCATION
THE COF HOLDER MAY INSPECT, TEST, AND PERFORM ROUTINE MX IF THEY HOLD THE FOLLOWING
CERTS:
REFRIGERATION OPERATING ENGINEER, HIGH PRESSURE OPERATING ENGINEER, AND NYS HIGH
6/8/2026
PRESSURE OPERATING ENGINEER.
4
06/08/2026
EXAM QUESTIONS AND ANSWERS
S-12 CITYWIDE SPRINKLER SYSTEMS, S12 sprinkler test
exam questions and answers latest 2026
THE __________ IS RESPONSIBLE TO MAINTAIN SPRINKLER SYS. AND TO DETERMINE QUALIFICATIONS.
OWNER
RECORDS OF ALL INSPECTIONS AND MX SHALL BE MAINTAINED ON PREMISES FOR A MIN. OF
__________ YEARS.
3
THE BUILDING OWNER SHALL ASSIGN A(N) ____________ TO COMPLY WITH REQUIREMENTS.
IMPAIRMENT COORDINATOR
REGULAR MX AND MINOR REPAIRS NOT AFFECTING MORE THAN ________ FLOOR(S) ARE CONSIDERED
PLANNED REMOVAL FROM SERVICE.
1
SHUTDOWNS AFFECTING MORE THAN _________ FLOOR(S) ARE CONSIDERED UNPLANNED OUT OF
SERVICE CONDITIONS.
1
6/8/2026
1
, S-12 CITYWIDE SPRINKLER SYSTEMS, S12 SPRINKLER TEST
06/08/2026
EXAM QUESTIONS AND ANSWERS
NOTIFICATION TO FDNY IS NOT REQUIRED, PROVIDED SYSTEM IS RETURNED TO SERVICE WITHIN ______
HOURS.
8
FOR UNPLANNED REMOVAL FROM SERVICE, THE COF HOLDER SHALL IMMEDIATELY REPORT CONDITION
TO THE ___________ AND THE FIRE DEPT.
OWNER OF THE BUILDING
IF A MINOR DEFECT IS OBSERVED, IT SHALL BE CORRECTED WITHIN _________ DAYS OR IT WILL BE
CONSIDERED AN IMPAIRMENT.
30
WHAT DOES "OOS" STAND FOR?
OUT OF SERVICE
OOS SYSTEMS SHALL BE IDENTIFIED BY PLACING ________ AT FIRE DEPT. CONNECTIONS, SYS. CONTROL
VALVES, AND FIRE COMMAND CENTER
TAGS
A _______ SHALL BE REQUIRED TO POST TAGS AT MAIN CONTROL VALVE AND ANY SECTIONAL VALVES.
MASTER FIRE SUPPRESSION PIPING CONTRACTOR
6/8/2026
__________ SHALL BE POSTED ON THE TAG INDICATING BOTH STATIC AND FLOW PRESSURES BEFORE
AND AFTER.
2
, S-12 CITYWIDE SPRINKLER SYSTEMS, S12 SPRINKLER TEST
06/08/2026
EXAM QUESTIONS AND ANSWERS
DRAIN TEST RESULTS
GREEN TAGS INDICATE THAT __________.
NO IMPAIRMENT WAS FOUND
GREEN TAGS WILL BE PLACED ON THE ____________.
MAIN CONTROL VALVE
SYSTEMS PARTIALLY OR FULLY OUT OF SERVICE SHALL HAVE A ____________ TAG PLACED ON THE
MAIN CONTROL VALVE.
RED
A _________ DISC OF 8-9 INCHES SHALL BE PLACED ON CONNECTIONS TO INDICATE THE SYSTEM IS
FULLY OUT OF SERVICE.
WHITE
A ________ DISC OF 8-9 INCHES SHALL BE PLACED ON CONNECTIONS TO INDICATE THE SYSTEM IS
PARTIALLY OUT OF SERVICE.
BLUE
THE IMPAIRMENT COORDINATOR WILL NOTIFY THE ___________ CARRIER, CENTRAL STATION AND
OCCUPANTS.
6/8/2026
INSURANCE
3
, S-12 CITYWIDE SPRINKLER SYSTEMS, S12 SPRINKLER TEST
06/08/2026
EXAM QUESTIONS AND ANSWERS
PRIOR TO RETURNING A SYS. TO SERVICE, THE ___________ SHALL ENSURE THAT NECESSARY TESTS
AND INSPECTIONS ARE CONDUCTED.
IMPAIRMENT COORDINATOR
GLYCERIN NOT GREATER THAN _________ PERCENT OR GLYCOL NOT GREATHER THAN ________
PERCENT SHALL BE USED TO PROTECT FROM FREEZING.
50, 40
THE COF NUMBER AND SIGNATURE OF COF HOLDER SHALL BE POSTED NEAR THE ____________.
MAIN CONTROL VALVE
__________ SHALL BE READILY AVAILABLE TO ANY REPRESENTATIVE OF THE FIRE DEPT. THESE ARE TO
BE MAINTAINED ON SITE FOR 3 YEARS.
RECORDS
FAILURE TO MAKE INSPECTIONS MAY RESULT IN __________ OF THE COF AND COURT PROCEEDINGS.
REVOCATION
THE COF HOLDER MAY INSPECT, TEST, AND PERFORM ROUTINE MX IF THEY HOLD THE FOLLOWING
CERTS:
REFRIGERATION OPERATING ENGINEER, HIGH PRESSURE OPERATING ENGINEER, AND NYS HIGH
6/8/2026
PRESSURE OPERATING ENGINEER.
4