NERC RC Exam Prep Questions With Well Elaborated Solutions A Balancing Authority has a normal load of around 8500 MW. Its most severe single contingency is a 700 MW coal-fired steam unit. At 0810, the ACE value was at -55 MW when a 600 MW generator in the Balancing Authority's northern area tripped off line due to a generator differential. This event resulted in a large negative ACE for the Balancing Authority. What value must ACE return to and in what time frame to avoid a DCS violation? A. -55 MW ACE in 15 minutes B. Zero ACE in 10 minutes C. -55 MW ACE in 10 minutes D. Zero ACE in 15 minutes - ANSWER -A. -55 MW ACE in 15 minutes If a Reserve Sharing Group member has experienced a Reportable Disturbance condition but does not call for reserve activation from other members, the entire group is considered to be in a disturbance condition. A. True B. False - ANSWER -B. False Turbine governors arrest Frequency deviations. Of the following, which control system compares and brings Net Actual Interchange back in line or as close to Net Scheduled Interchange as possible? A. Load Response B. Flat Frequency Control C. Automatic Generation Control D. Automatic Voltage Regulation - ANSWER -C. Automatic Generation Control Automatic Generation Control uses the ACE equation to ________. A. Minimize Inadvertent Interchange among Balancing Authority areas B. Provide frequency support for the Interconnection C. Both ANSWERs are correct D. Neither ANSWER is correct - ANSWER -C. Both ANSWERs are correct Which part of the ACE equation reflects Pseudo-Ties values? A. Scheduled Net Interchange component, NIS B. Actual Net Interchange component, NIA C. Frequency component, FA - FS D. Pseudo-Ties are not included in the ACE equation. - ANSWER -B. Actual Net Interchange component, NIA A Balancing Authority's frequency indication has become erratic and unreliable. Which AGC mode should the Balancing Authority operate in? A. Manual Control B. Flat Frequency Control C. Tie Line Bias Control D. Flat Tie Line Control - ANSWER -D. Flat Tie Line Control Which of the following is required to ensure Balancing Authority operators are aware of errors associated with data used for calculating Reporting ACE, and how to mitigate those errors? A. An Operating Process for identifying and mitigating errors B. A separate, independent alarm system for ACE data errors C. A backup Reporting ACE calculation using data from an independent source D. Monthly training on identifying and mitigating errors - ANSWER -A. An Operating Process for identifying and mitigating errors What is the availability requirement per calendar year for frequency metering used for calculating Reportable ACE? A. 99.50% B. 99.00% C. 99.95% D. .995% - ANSWER -C. 99.95% A Balancing Authority has discovered one tie line meter reading is off by 30 MW, causing the ACE values to be incorrect. What should be done to temporarily adjust for the error until the meter can be calibrated or repaired? A. Take the numbers from the incorrect tie line and insert them into the NIS portion of the ACE equation B. Use the IME portion of the equation to adjust for the meter error C. Change the AGC mode to Flat Frequency Control D. Change the Frequency Bias part of the ACE equation to reflect the error - ANSWER -B. Use the IME portion of the equation to adjust for the meter error Which of the following terms of the ACE equation is not affected by frequency? A. NIA B. FA C. B D. All terms are affected - ANSWER -C. B Interchange Schedules are only between adjacent Balancing Authorities, with the exception of Dynamic Schedules. True or False? A. True B. False - ANSWER -A. True What condition must be met prior to an Arranged Interchange transitioning to an Implemented status? A. Energy delivered must be paid for B. Transaction that are denied have a reason. C. The Reliability Coordinator provides its approval

Show more Read less
Institution
NERC RC
Course
NERC RC

Content preview

NERC RC Exam Prep Questions With
Well Elaborated Solutions
A Balancing Authority has a normal load of around 8500 MW. Its most severe
single contingency is a 700 MW coal-fired steam unit. At 0810, the ACE value
was at -55 MW when a 600 MW generator in the Balancing Authority's northern
area tripped off line due to a generator differential. This event resulted in a large
negative ACE for the Balancing Authority. What value must ACE return to and in
what time frame to avoid a DCS violation?

A. -55 MW ACE in 15 minutes
B. Zero ACE in 10 minutes
C. -55 MW ACE in 10 minutes
D. Zero ACE in 15 minutes - ANSWER -A. -55 MW ACE in 15 minutes

If a Reserve Sharing Group member has experienced a Reportable Disturbance
condition but does not call for reserve activation from other members, the entire
group is considered to be in a disturbance condition.

A. True
B. False - ANSWER -B. False

Turbine governors arrest Frequency deviations. Of the following, which control
system compares and brings Net Actual Interchange back in line or as close to Net
Scheduled Interchange as possible?

A. Load Response
B. Flat Frequency Control
C. Automatic Generation Control
D. Automatic Voltage Regulation - ANSWER -C. Automatic Generation Control

Automatic Generation Control uses the ACE equation to ________.

A. Minimize Inadvertent Interchange among Balancing Authority areas

,B. Provide frequency support for the Interconnection
C. Both ANSWERs are correct
D. Neither ANSWER is correct - ANSWER -C. Both ANSWERs are correct

Which part of the ACE equation reflects Pseudo-Ties values?

A. Scheduled Net Interchange component, NIS
B. Actual Net Interchange component, NIA
C. Frequency component, FA - FS
D. Pseudo-Ties are not included in the ACE equation. - ANSWER -B. Actual Net
Interchange component, NIA

A Balancing Authority's frequency indication has become erratic and unreliable.
Which AGC mode should the Balancing Authority operate in?

A. Manual Control
B. Flat Frequency Control
C. Tie Line Bias Control
D. Flat Tie Line Control - ANSWER -D. Flat Tie Line Control

Which of the following is required to ensure Balancing Authority operators are
aware of errors associated with data used for calculating Reporting ACE, and how
to mitigate those errors?

A. An Operating Process for identifying and mitigating errors
B. A separate, independent alarm system for ACE data errors
C. A backup Reporting ACE calculation using data from an independent source
D. Monthly training on identifying and mitigating errors - ANSWER -A. An
Operating Process for identifying and mitigating errors

What is the availability requirement per calendar year for frequency metering used
for calculating Reportable ACE?

A. 99.50%
B. 99.00%

,C. 99.95%
D. .995% - ANSWER -C. 99.95%

A Balancing Authority has discovered one tie line meter reading is off by 30 MW,
causing the ACE values to be incorrect. What should be done to temporarily adjust
for the error until the meter can be calibrated or repaired?

A. Take the numbers from the incorrect tie line and insert them into the NIS
portion of the ACE equation
B. Use the IME portion of the equation to adjust for the meter error
C. Change the AGC mode to Flat Frequency Control
D. Change the Frequency Bias part of the ACE equation to reflect the error -
ANSWER -B. Use the IME portion of the equation to adjust for the meter error

Which of the following terms of the ACE equation is not affected by frequency?

A. NIA
B. FA
C. B
D. All terms are affected - ANSWER -C. B

Interchange Schedules are only between adjacent Balancing Authorities, with the
exception of Dynamic Schedules. True or False?

A. True
B. False - ANSWER -A. True

What condition must be met prior to an Arranged Interchange transitioning to an
Implemented status?

A. Energy delivered must be paid for
B. Transaction that are denied have a reason.
C. The Reliability Coordinator provides its approval

, D. Sink Balancing Authority must confirm the transaction status is Confirmed. -
ANSWER -D. Sink Balancing Authority must confirm the transaction status is
Confirmed.

What is the purpose of conducting a reliability assessment for an Arranged
Interchange?

A. Ensure contingency reserves are met
B. Determine the economic benefit
C. Ensure Tag is submitted
D. Determine the capability of supporting the magnitude of the Interchange -
ANSWER -D. Determine the capability of supporting the magnitude of the
Interchange

When an Interchange Transaction is approved, the full amount will travel on the
reserved path per the E-tag.

A. True
B. False - ANSWER -B. False

The communication and coordination of the Interchange process is carried out by
the Interchange Authority. The Interchange Authority is best described as which of
the following?

A. Generation Control of Actual Interchange
B. Energy Management System
C. A computer software program of Electronic Tagging
D. Interconnection Distribution Calculator - ANSWER -C. A computer software
program of Electronic Tagging

When a transaction is approved and becomes Confirmed Interchange, which
entities must be notified?

A. Only the Source and Sink Balancing Authorities and the Reliability Coordinator

Written for

Institution
NERC RC
Course
NERC RC

Document information

Uploaded on
May 21, 2026
Number of pages
63
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

$16.99
Get access to the full document:

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
TheExamMaestro Teachme2-tutor
View profile
Follow You need to be logged in order to follow users or courses
Sold
148
Member since
2 year
Number of followers
5
Documents
3507
Last sold
4 days ago
STA

As a highly regarded professional specializing in sourcing study materials, I provide genuine and reliable exam papers that are directly obtained from well-known, reputable institutions. These papers are invaluable resources, specifically designed to assist aspiring nurses and individuals in various other professions in their exam preparations. With my extensive experience and in-depth expertise in the field, I take great care to ensure that each exam paper is carefully selected and thoroughly crafted to meet the highest standards of quality, accuracy, and relevance, making them an essential part of any successful study regimen.

Read more Read less
3.6

18 reviews

5
9
4
2
3
2
2
0
1
5

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions