An organization has a surplus of project dollars in the operating budget. The senior
leader's decision is to fund one more project with the remaining funds. Of the three
projects proposed, one of the projects was selected without evaluation of feasibility
or viability.
Which non-numeric model is this leader using? - Answer✔️Sacred cow
Each project team member generated a series of questions to evaluate three
projects. The checklist was compiled into one list based on frequency of question
content, such as personnel, materials, experience, and time. The more frequent the
question content, the more likely the questions would be asked first.
Which two benefits result from this checklist approach? - Answer✔️(1) Operational
impact has been built in (2) Strategic impact has been integrated.
Each project team member generated a series of questions to evaluate three
projects. A checklist was then compiled into one list based on the frequency of
question content, such as personnel, materials, experience, and time.
What is a disadvantage of using this checklist approach? - Answer✔️Biases have
not been eliminated.
To calculate money's worth today compared to in the future - Answer✔️Time value
of money
, 2
To calculate future cash flows using time and interest rate - Answer✔️Internal rate
of return
To calculate whether revenue tomorrow is greater than costs today - Answer✔️Net
present value
To calculate the alternative use of money - Answer✔️Opportunity cost
What is the time value of money? - Answer✔️The concept that a dollar today is
worth a dollar, but a dollar in a year will be worth less than a dollar
What is internal rate of return? - Answer✔️The discount amount when present
value of cash intake equals the original investment
Which two processes are considered iterative processes? - Answer✔️(1) Planning
(2) Executing
Which activity is accomplished as part of the planning process of a project? -
Answer✔️Finalizing the project budget
Which activity is accomplished as part of the planning process of a project? -
Answer✔️Finalizing the project schedule
Which activity is accomplished during the closing process of a project? -
Answer✔️Reconciling the vendor accounts
, 3
Which activity is performed during the creating part of the initiating process? -
Answer✔️Drafting the project charter
Which activity is accomplished as part of the executing process of a project? -
Answer✔️Implementing the project plan
Which process involves determining who the project's stakeholders are? -
Answer✔️The initiating process
What information does this resource histogram display that can help during the
planning phase of the project? - Answer✔️Opportunities to level resource usage
patterns
Which tool could a project manager use to ensure that the project team will address
the items that are important when developing and defining the project's scope? -
Answer✔️Checklist
A project manager wants to understand and document the approvals that must be
obtained for each work package in the work breakdown structure (WBS).
Which tools document the approval requirements for each work package? -
Answer✔️(1) Project statement of work (SOW) (2) Requirements traceability
matrix (RAM)
The general manager of a hotel has asked for a project to put in new landscaping
around the building. The project manager has constructed a high-level work
breakdown structure (WBS) for the project, which is provided below.
WBS ID Description
, 4
1.0 Landscaping
1.1 Plans
1.2 Site preparation
1.3 Sprinklers
1.4 Sidewalks and curbing
1.5 Planting
Which activity would it be logical to add to the approved high-level WBS to
provide more detail on the work to be accomplished? - Answer✔️1.5.1 Lay sod
Closing Phase - Answer✔️Project outcomes are delivered to the customer and/or
sponsor and the customer and/or sponsor evaluates them to determine if they are
acceptable - deliverables are ready, the budget and time requirements are met and
quality is achieved, and lessons learned are documented
PM Methods - Answer✔️PERT, CPM, critical chain, waterfall, and PRINCE2
PERT (Project evaluation and review technique) - Answer✔️Developed in 1950 to
estimate activity on Navy's Polaris missile project.
CPM (Critical path method) - Answer✔️Developed by DuPont to help with project
in manufacturing. Similar to PERT but assumes that estimates do not vary and time
can be reliably estimated
Critical chain project management (CCPM) - Answer✔️Work each resource is
expected to complete is checked to verify that the resource will be capable and
available when needed. Time buffers are built into the schedule to handle situations
when the critical resources fall behind or aren't available