COSC 275 FINAL EXAM REVIEW QUESTIONS AND ANSWERS (GRADED A+)

Rating
-
Sold
-
Pages
7
Grade
A
Uploaded on
19-05-2026
Written in
2025/2026

Quantification - ANSWER-In estimating an activity to translate project scope information into resource quantities suitable for costing. In the engineering and construction industry, a takeoff is a specific type of quantification that is a measurement and listing of quantities of materials from drawings Quantities - ANSWER-Measured amounts of construction items expressed in their customary units. Estimating - - ANSWER-The anticipated cost of materials, labor, equipment, or any combination of these for a proposed construction project. Activity - - ANSWER-In critical path method (CPM) scheduling, a task or item of work required to complete a project. Also called task.

Show more Read less
Institution
COSC 275
Course
COSC 275

Content preview

COSC 275 FINAL EXAM REVIEW
QUESTIONS AND ANSWERS
(GRADED A+)
Quantification - ANSWER-In estimating an activity to translate project scope
information into resource quantities suitable for costing. In the engineering and
construction industry, a takeoff is a specific type of quantification that is a
measurement and listing of quantities of materials from drawings

Quantities - ANSWER-Measured amounts of construction items expressed in their
customary units.

Estimating - - ANSWER-The anticipated cost of materials, labor, equipment, or any
combination of these for a proposed construction project.

Activity - - ANSWER-In critical path method (CPM) scheduling, a task or item of work
required to complete a project. Also called task.

Project - - ANSWER-the job as a whole

Scope - - ANSWER-An accurate, detailed, and concise description of the work to be
performed by the contractor, the owner, and third parties in a construction contract.

Measurement - - ANSWER-A quantity survey from plans or a field survey of work to
be done.

Material - - ANSWER-Any product or substance specified for use in the construction
of a project.

Drawings - - ANSWER-The portion of the contract documents that gives a graphic
representation of the work to be done in the construction of a project.

Specifications - - ANSWER-a detailed and exact statement of particulars, especially
a statement prescribing materials, dimensions, and workmanship for something to be
built or installed

Dimensions - - ANSWER-the distance between two points, lines, or planes

Workmanship - - ANSWER-the quality of work performed

Specs - - ANSWER-contraction of specifications

Area method - - ANSWER-A construction cost estimating system employing
unitsquare foot costs multiplied by the adjusted gross floor area of a building.

, Linear measurement - - ANSWER-A unit or system of units for measuring length: 12"
= 1', 3' = 1 yard, 1 yard = 0.9144 meters, 1 mile = 5,280 feet.

Length - - ANSWER-the longest dimension of an object

Yard - - ANSWER-A unit of length in the English system equal to 3'. A measure of
concrete. One cubic yard = 3' x 3' x 3' in volume, or 27 cubic feet. A term applied to
that part of a plot not occupied by the building or driveway.

Where do i start? Scope? - ANSWER-First thing you need to know before you make
a quantitative estimate you need to know the scope (plans, specs, and simply put the
list of things you have to do in order of sequence of when they need to be done in
relation to each other)
Second step is to begin take offs but preparations are necessary such as contract
documents
You quantify it in the same way and order that you build it

Specification or specs - - ANSWER-Documents that define the qualitative
requirements for products, materials, and workmanship upon which the contract for
construction is based.

Contract for construction - - ANSWER-An agreement between owner and contractor
whereby the contractor agrees to construct the owner's project in accordance with
the contract documents, within a specified amount of time, and for consideration to
be paid by the owner as mutually agreed.

Area - - ANSWER-A measurement of a given planar region or of the surface of a
solid. A particular part of a building that has been set aside for a specific purpose.


Divisions of construction - ANSWER-Division 0 - general condition
Division 1 - General requirements
Division 2 - Existing condition
Division 3 - concrete
Division 4 - masonry
Divisio n 5 - metal
Division 6 - wood and plastics
Division 7 - thermal and moisture protection
Division 8 - doors and windows
Division 9 - finishes
Division 10 - specialties
Division 11 - Equipment
Division 12 - furnishings
Division 13 - Special construction
Division 31 - earthworks
Division 32 - exterior improvements

Specification types - ANSWER-See "Old CSI Specification Divisions" for old specs,
goes from 1-16

Written for

Institution
COSC 275
Course
COSC 275

Document information

Uploaded on
May 19, 2026
Number of pages
7
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

$13.99
Get access to the full document:

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF


Also available in package deal

Thumbnail
Package deal
COSC 275 EXAMS BUNDLE( PACKAGE DEAL) 2026/27!!
-
15 2026
$ 78.33 More info

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
NursingTutor1 West Virginia University
View profile
Follow You need to be logged in order to follow users or courses
Sold
1697
Member since
3 year
Number of followers
1073
Documents
18441
Last sold
3 days ago
Nursing Tutor

Paper Due? Worry not. Hello. Welcome to NursingTutor. Here you\'ll find verified study materials for your assignments, exams and general school work. All papers here are graded A to help you get the best grade. Also, I am a friendly person so, do not hesitate to send a message in case you have a query. I wish you Luck.

3.9

459 reviews

5
217
4
79
3
92
2
21
1
50

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions