EXAM COMPLETE 300 QUESTIONS AND CORRECT
DETAILED ANSWERS (VERIFIED ANSWERS) |ALREADY
GRADED A+!!!!
Which of the following documents is utilized for correspondence
between the A/E or Owner and the Contractor?
A. Job Diary
B. Memorandum
C. Construction Report
D. Formal Business Letter - ANSWERd
Which of the following documents is used for correspondence
between the home office and the job site?
A. Job Diary
B. Memorandum
C. Construction Report
,D. Formal Business Letter - ANSWERb
What is the best time to distribute the Working Agenda to the
Participants? A. As a follow-up to the meeting
B. At the beginning of the meeting
C. About one day after the meeting
D. About one day prior to the meeting - ANSWERd
Which document describes the Suggested Agenda for the
Preconstruction Meeting?
A. General Conditions
B. General Requirements
C. TechnicalSpecifications
D. Supplementary Conditions - ANSWERb
,What is the best time to distribute the Meeting Minutes to the
Participants?
A. At the beginning of the meeting
B. About one day after the meeting
C. About one hour prior to the meeting
D. About one day prior to the meeting - ANSWERb
Which of the following descriptions are the primary content items
for the meeting minutes?
A. To, from, project, date, time place and
subject
B. Purpose, specific objectives, time frame,
topical headings with paragraph, role
C. Objective clear and measurable,
attendance, role of each person, their
, expertise
D. Attendance, topical headings with
paragraph stating person assigned, completion - ANSWERd
Which of the following descriptions are the content items for the
working agenda?
A. Plan with goals and specific activities,
priority, time needed, scheduled events
B. Purpose, specific objectives, time frame,
topical headings with paragraph, role
C. Activity description, days, information
needed crew size, material & equipment
D. Attendance, topical headings with
paragraph stating person assigned, completion - ANSWERb