Generator ratings specify the __________ and ___________ at which they can
operate safely.
A) temperature; voltage
B) torque angle; voltage
C) System Operating Limits; Interconnection Operating Limits
D) voltage; frequency - CORRECT ANSWER ✔✔- voltage; frequency
Which of the following is one of the criteria used to determine the System
Operating Limit?
A) Setting appropriate voltage levels to withstand various contingencies.
B) Identifying equipment minimum loading capabilities.
C) Recognizing operator limitations.
D) Identifying how transformers respond to severe fluctuations in frequency. -
CORRECT ANSWER ✔✔- Setting appropriate voltage levels to withstand various
contingencies.
1|Page
,NERC Standard CIP-001 is applicable to which of the following entities?
A) Generator Operators and Load Serving Entities
B) Balancing Authorities and Transmission Operators
C) All of the choices provided
D) Reliability Coordinators - CORRECT ANSWER ✔✔- All of the choices provided
Sabotage events are often difficult to identify, therefore, entities are required to
have __________ available for operating personnel.
A) procedures
B) contact information
C) FBI or RMCP
D) displays - CORRECT ANSWER ✔✔- procedures
NERC requires each Reliability Coordinator, Balancing Authority, Transmission
Operator, Generator Operator, and Load Serving Entity shall have procedures for
the recognition of and for making _______________ aware of sabotage events on
its facilities and multi-site sabotage affecting larger portions of the
Interconnection.
A) Regional Reliability Organizations
B) DOE
C) NERC
D) their operating personnel - CORRECT ANSWER ✔✔- their operating personnel
2|Page
, NERC requires each Reliability Coordinator, Balancing Authority, Transmission
Operator, Generator Operator and Load Serving Entity to establish
communications contacts, as applicable with local Federal Bureau of Investigation
(FBI) or Royal Canadian Mounted Police (RCMP) officials and develop
_____________ as appropriate to their circumstances.
A) media relations
B) reporting procedures
C) governmental operating guidelines
D) step by step procedures to stop the sabatoge - CORRECT ANSWER ✔✔-
reporting procedures
In the event of sabotage on the transmission or generation system, it is highly
likely that the procedure developed for CIP-001 will include the Disturbance
Reporting procedure your organization has developed in response to NERC
Standard category ________.
A) EOP
B) TOP
C) CIP
D) IRO - CORRECT ANSWER ✔✔- EOP
Disturbance events that are suspected to be caused by sabotage, shall be
reported to _____________.
A) the appropriate systems
B) governmental agencies
3|Page