QM 6655 Ch. 8 QUESTION AND ANSWERS 100% CORRECTQM 6655 Ch. 8 QUESTION AND ANSWERS 100% CORRECTWhich aspects of a project may be finalized once resources are applied to a project plan? - ANSWER-1. A baseline project schedule. 2. The project baseline budget What are the primary goals of "resource smoothing" within a project plan? - ANSWER-1. Increase utilization percentage of resources used. 2. Potentially reduce the maximum amount of a needed resource. In resource-constrained scheduling, there may not be enough resources available and the late start of some activities could be delayed. What is the most likely result of

Show more Read less
Institution
QM 6655 Ch. 8
Course
QM 6655 Ch. 8

Content preview

QM 6655 Ch. 8 QUESTION AND
ANSWERS 100% CORRECT
Which aspects of a project may be finalized once resources are applied to a project
plan? - ANSWER-1. A baseline project schedule.
2. The project baseline budget

What are the primary goals of "resource smoothing" within a project plan? -
ANSWER-1. Increase utilization percentage of resources used.
2. Potentially reduce the maximum amount of a needed resource.

In resource-constrained scheduling, there may not be enough resources available
and the late start of some activities could be delayed. What is the most likely result of
these issues? - ANSWER-The duration of the project may be increased.

When there is a shortage of resources while planning a project, resource
dependency will: - ANSWER-take priority over a technical/network dependency.

In projects the availability or unavailability of _________ will often influence the way
projects are managed. - ANSWER-resources

Which statement best describes why resources need to be incorporated into a
project precedence network plan? - ANSWER-Project network times cannot become
a schedule until resources have been assigned.

Why is "minimum slack" the first criteria for the parallel method heuristic? -
ANSWER-Critical activities will have the minimum amount of slack in a network.
Reason:
Hence, the heuristic is trying to protect the scheduled end date

People are more efficient if they: - ANSWER-focus on one project at at time

A perfectly leveled project can result in every activity becoming critical. - ANSWER-
High

Heuristics do not always yield an optimal schedule, but they are very capable of
yielding a schedule for very complex networks with many types of resources. -
ANSWER-

The planned network and activity project duration times found in previous chapters
did not take into account resource _________ and ____________. - ANSWER-
usage and availability

A schedule is said to be "resource constrained" under which of the following
circumstances? - ANSWER-1. When the precedence network duration cannot be
met due to lack of resources.
2. When the assignment of resources to one or more activities is overcommitted.

, In scheduling terms, time constrained means project duration is ________ and
resources are ________. - ANSWER-1. fixed
2. flexible

A deficit of _______ can significantly alter project dependency relationships,
completion dates, and project costs. - ANSWER-resources

Identify two limiting assumptions that have been used in this chapter to improve the
ease of demonstrating resource allocation. - ANSWER-1. Resources assigned to a
task cannot be changed.
2. Splitting activities is not allowed.

People, equipment, and material are _____ that must be managed during a project. -
ANSWER-resources

Basically all ________ techniques delay noncritical activities by using positive slack
to reduce peak demand and fill in the valleys for the resources. - ANSWER-leveling

What is a resource schedule used for? - ANSWER-to assign time-phased costs

Assigning proper resources to activities is accomplished by using information
developed during what process? - ANSWER-Work package development
Reason:
By definition, a work package must be able to define time and cost requirements.

Which of the following is a goal of smoothing? - ANSWER-Minimize fluctuations in
resource demand.
Reason:
This is one of the three goals of smoothing.

In scheduling terms, resource constrained means resources are _____ and time is
_______ . - ANSWER-1. fixed
2. flexible

Which of the following is true of smoothing/leveling resources in a time-constrained
project? - ANSWER-Loss of scheduling flexibility
Reason:
Due to a reduction in slack.

________ refers to interrupting work on one task and assigning the resources to
work on a different task for a period of time, then reassigning them to work on the
original task. - ANSWER-splitting

The resource scheduling problem is a large, combinatorial one. Thus, most
scheduling problems are solved using ______ . - ANSWER-heuristics

Scheduling time-constrained projects focuses on resource _____? - ANSWER-
utilization

Written for

Institution
QM 6655 Ch. 8
Course
QM 6655 Ch. 8

Document information

Uploaded on
April 24, 2026
Number of pages
6
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

$15.49
Get access to the full document:

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF


Also available in package deal

Thumbnail
Package deal
QM 6655 EXAMS BUNDLE WITH COMPLETE SOLUTIONS
-
3 2026
$ 22.38 More info

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
NursingTutor1 West Virginia University
View profile
Follow You need to be logged in order to follow users or courses
Sold
1697
Member since
3 year
Number of followers
1073
Documents
18441
Last sold
4 days ago
Nursing Tutor

Paper Due? Worry not. Hello. Welcome to NursingTutor. Here you\'ll find verified study materials for your assignments, exams and general school work. All papers here are graded A to help you get the best grade. Also, I am a friendly person so, do not hesitate to send a message in case you have a query. I wish you Luck.

3.9

459 reviews

5
217
4
79
3
92
2
21
1
50

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions