What is a BCM? -
correct answer ✅Bar Chart Method
What does the BCM consist of? -
correct answer ✅1. Horizontal time scale and vertical listing of
project activities
2. Bars are drawn to show the time span of work activities
What is a CPM? -
correct answer ✅Critical path method
What is CPM used for? -
correct answer ✅Represents the sequence and independence of
work activities and time, factors in any constraints and restrictions.
Clearly defines work activities
What is float considered in CPM? -
correct answer ✅Defined as the amount of time between earliest
start date and latest end date that doesn't affect schedule
completion date
Documentation Exam Questions &
Answers (Grade A+)
What is a BCM? -
correct answer ✅Bar Chart Method
What does the BCM consist of? -
correct answer ✅1. Horizontal time scale and vertical listing of
project activities
2. Bars are drawn to show the time span of work activities
What is a CPM? -
correct answer ✅Critical path method
What is CPM used for? -
correct answer ✅Represents the sequence and independence of
work activities and time, factors in any constraints and restrictions.
Clearly defines work activities
What is float considered in CPM? -
correct answer ✅Defined as the amount of time between earliest
start date and latest end date that doesn't affect schedule
completion date