● General Conditions. Answer: Contract provisions establishing basic rights and
responsibilities

● AIA Document G202. Answer: Standard form for project application and certification for
payment

● Application for Payment. Answer: Request submitted by contractor for payment of work
completed

● Certificate for Payment. Answer: Document issued by architect certifying payment amount
due

● Schedule of Values. Answer: Breakdown of contract sum into portions for each
component

● Stored Materials. Answer: Materials purchased but not yet incorporated into the work

● Retainage. Answer: Percentage of payment withheld until project completion

● Substantial Completion. Answer: Stage when owner can occupy or use work for intended
purpose

● Final Completion. Answer: When all work is complete and contract fully performed

● Change Order. Answer: Written modification to the contract documents

● Construction Change Directive. Answer: Order requiring change in work prior to
agreement on adjustment

● Payment Application Date. Answer: Date by which contractor must submit payment
application

● Architect's Action. Answer: Review and certification or rejection of payment application

● Owner's Payment Period. Answer: Time within which owner must pay after architect's
certificate

, ● Work in Place. Answer: Construction work installed and incorporated into the project

● Percentage Complete. Answer: Proportion of work finished for each schedule of values
item

● Previous Applications. Answer: Prior payment requests used to calculate cumulative
amounts

● Net Amount Due. Answer: Total certified amount less previous payments and retainage

● Contract Sum. Answer: Total amount payable to contractor under contract documents

● Allowances. Answer: Specified amounts included in contract sum for particular items

● Unit Prices. Answer: Predetermined rates for specific quantities of work

● Current Payment Due. Answer: Amount payable for work completed in current period

● Column Totals. Answer: Sum of values in schedule of values columns

● Scheduled Value. Answer: Original contract amount allocated to specific work item

● Work Completed This Period. Answer: Portion of work item finished in current application
period

● Materials Presently Stored. Answer: Value of materials on site but not yet installed

● Total Completed and Stored to Date. Answer: Cumulative work and materials through
current period

● Balance to Finish. Answer: Remaining value of work not yet completed or stored

● Retainage Percentage. Answer: Rate at which funds are withheld from payments

● Total Retainage. Answer: Cumulative amount withheld from all payments to date

● Total Earned Less Retainage. Answer: Amount contractor has earned minus retention

● Amount Certified. Answer: Sum architect approves for payment in current period

● Contractor's Certification. Answer: Statement attesting to accuracy of payment
application

● Architect's Certification. Answer: Professional verification of amounts and work
completed

Document information

Uploaded on
April 22, 2026
Number of pages
6
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers
$12.99

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Sold
0
Followers
0
Items
716
Last sold
-


Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions