NEVADA (NV) GENERAL ENGINEERING CONTRACTOR EXAM 2026
Complete Practice Test — 300 Questions with Answers & EXPERT RATIONALE
This practice test is designed to help you build confidence and master exam
material through repeated exposure to realistic questions. Work through each
question independently before checking the correct answer and EXPERT
RATIONALE — that active recall process is what drives real retention.
Question 1 Under Nevada law, which of the following is required before a general
engineering contractor can legally begin work on a project?
A. A signed contract with the property owner
B. Proof of general liability insurance
C. A valid contractor's license issued by the Nevada State Contractors Board
D. A business plan filed with the Secretary of State
E. A surety bond of at least $500,000
Correct Answer: C EXPERT RATIONALE: Nevada Revised Statutes (NRS) Chapter
624 requires that any contractor performing work in Nevada must hold a valid license
issued by the Nevada State Contractors Board (NSCB) before commencing any work.
Question 2 The Nevada State Contractors Board (NSCB) is authorized to do which
of the following?
A. Issue building permits to contractors
B. Suspend or revoke a contractor's license for violations
C. Set wage rates for construction workers
,D. Approve architectural plans for public projects
E. Negotiate contracts on behalf of contractors
Correct Answer: B EXPERT RATIONALE: The NSCB has authority under NRS 624
to discipline licensees, including suspension or revocation of licenses for violations such
as fraud, incompetence, or failure to comply with regulations.
Question 3 A contractor's license in Nevada must be renewed every:
A. Six months
B. One year
C. Two years
D. Three years
E. Four years
Correct Answer: C EXPERT RATIONALE: Nevada contractor licenses are valid for
two years and must be renewed biennially to remain in good standing with the NSCB.
Question 4 Which of the following best describes the role of a "qualifier" on a
Nevada contractor's license?
A. The person who signs construction contracts
B. The financial guarantor of the contractor's work
C. The individual who meets the experience and examination requirements
on behalf of the licensed entity
D. The project manager assigned to each job site
E. The insurance agent who underwrites the contractor's policy
Correct Answer: C EXPERT RATIONALE: A qualifier is the individual whose
knowledge, experience, and exam performance qualifies the contracting business for
licensure. They are responsible for supervising the work of the license.
,Question 5 Under Nevada law, if a contractor abandons a project without legal
justification, the NSCB may:
A. Only issue a written warning
B. Require the contractor to post additional bond
C. Revoke or suspend the contractor's license
D. Require the contractor to complete a training course
E. Transfer the license to another qualifier
Correct Answer: C EXPERT RATIONALE: Abandoning a project without legal
excuse is grounds for disciplinary action by the NSCB under NRS 624.300, which may
include license suspension or revocation.
Question 6 What is the minimum liability insurance requirement for a Nevada
general engineering contractor?
A. $100,000 per occurrence
B. $500,000 per occurrence
C. $1,000,000 per occurrence
D. $250,000 per occurrence
E. No minimum is required by state law
Correct Answer: B EXPERT RATIONALE: The NSCB requires a minimum of
$500,000 in general liability insurance per occurrence for contractors performing
commercial work in Nevada.
Question 7 Which of the following entities is exempt from Nevada contractor
licensing requirements?
A. A property owner performing work on their own single-family residence
, B. A subcontractor working under a general contractor
C. An out-of-state contractor working on a federally funded project
D. A construction manager overseeing multiple projects
E. A general engineering firm performing roadwork
Correct Answer: A EXPERT RATIONALE: NRS 624.031 provides an exemption for
owners who perform work on their own single-family dwelling, provided they do not hire
unlicensed workers and the work is not intended for sale.
Question 8 When must a Nevada contractor notify the NSCB of a change in their
qualifying agent?
A. Within 6 months
B. Within 90 days
C. Within 30 days
D. Within 60 days
E. At the time of license renewal
Correct Answer: C EXPERT RATIONALE: NRS 624.270 requires licensees to notify
the NSCB within 30 days of a change in the qualifying agent to ensure continued
compliance and proper oversight.
Question 9 Under the Nevada Prompt Payment Act, a contractor must pay a
subcontractor within how many days of receiving payment from the owner?
A. 30 days
B. 10 days
C. 15 days
D. 21 days
E. 7 days