CDT Exam Prep


Which of the following is not a management expertise that contractors bring to the project delivery
process?

A. Identifying codes and regulations applicable to the design

B. Experience with managing a construction budget in a risk-based setting

C. Knowledge of factors that influence cost, time, and quality

D. Ability to manage multiple subcontractors and suppliers - Answer-A. Identifying codes and regulations
applicable to the design.



Which of the following is a stage of the Facility Life Cycle?

A. Project Conception

B. Project Permitting

C. Facility Maintenance

D. Preliminary Project Description - Answer-A. Project Conception



The written formats can each be employed for a variety of applications; the chief advantage of using
standard formats is:

A. a standardizes numbering system.

B. a standardized location withing the Drawings for subject matter.

C. a standardized set of contracts between the owner and contractor.

D. a standardized means of organizing, storing, retrieving, and communication an enormous body of
data. - Answer-D. a standardized means of organizing, storing, retrieving, and communication an
enormous body of data.

,The design stage of a project includes all of the following except which one?

A. Preliminary project description

B. Engineering design criteria

C. Feasibility studies

D. Outline specifications - Answer-C. Feasibility studies



Which of the following is a component of the National CAD Standard (NCS)?

A. OmniClass

B. CSI CAD Layer Guidelines

C. MasterFormat

D. CSI Uniform Drawing System - Answer-D. CSI Uniform Drawing System



Which of the following entities assumes the bulk of risk in a construction project?

A. Owner Team

B. Supplier Team

C. Design Team

D. Contractor Team - Answer-A. Owner Team



Which of the following entities is responsible for design compliance with the authorities having
jurisdiction?

A. Owner

B. Architect

C. Plan Reviewer

D. Contractor - Answer-B. Architect

,Which of the following will the courts use to interpret specifications in the same manner as they
interpret contracts?

A. Autonomy to contract.

B. Professional negligence.

C. General takes precedence over specific.

D. Construction for the drafter. - Answer-A. Autonomy to contract.



It is not uncommon for a public owner to dictate the design and construction process for the different
delivery methods, which of the following are examples of this?

A. How safety will be controlled on the project site

B. How the architect's construction administration and the contractor's project management will be
conducted

C. AJH submittal requirements

D. Which financial institutions will provide bonding for the contractor's performance - Answer-B. How
the architect's construction administration and the contractor's project management will be conducted



What establishes the relationship between the Contractor and the A/E?

A. Applicable laws and regulations

B. Signed agreement

C. Third-party obligations

D. Special conditions - Answer-C. Third-party obligations



In the substitution process, the onus for researching and documenting the acceptability of the proposed
substitution is the responsibility of the:

A. Contractor

B. Owner

C. A/E

, D. Entity requesting substitution - Answer-D. Entity requesting substitution



Who's duty is it to ascertain that the Contract Documents are in accordance with the applicable building
codes?

A. Subcontractor

B. Contractor

C. Owner

D. A/E - Answer-D. A/E



Instructions to Bidders:

A. Are used only on private projects

B. Frequently are standard printed forms

C. May include the geotechnical report as an attachment

D. Are binding upon the contractor - Answer-B. Frequently are standard printed forms



Which of the following would be included in the Information Available to Bidders?

A. Bid security information

B. Environmental impact statement

C. Contract Times to complete the Work

D. Description of the Work - Answer-B. Environmental impact statement



The contractual relationship governed by the Conditions of the Contract is between:

A. Owner and Contractor

B. Architect/Engineer and Contractor

C. Owner and Subcontractors

D. Architect/Engineer and Subcontractors - Answer-A. Owner and Contractor

Document information

Uploaded on
April 12, 2026
Number of pages
58
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers
$24.49

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
Zanaya
4.5
(12)
Sold
76
Followers
29
Items
10149
Last sold
1 week ago


Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions