WGU C844 TASK 1 AND 2 COMBINED
ACTUAL EXAM PAPER 2026 QUESTIONS
WITH ANSWERS GRADED A+
• title().
Answer: capitalizes first letter of each word
• Critical chain project management (CCPM).
Answer: Work each resource is expected to complete is checked to verify
that the resource will be capable and available when needed. Time buffers
are built into the schedule to handle situations when the critical resources
fall behind or aren't available
• Control Schedule, Tools & Techniques.
Answer: Data analysis, Critical path method, Project management
information system, Resource optimization, Leads and lags, Schedule
compression
• from csv import reader as scvreader.
Answer: mports individual function from a module and assigns it a new
name
• Operating Necessity.
Answer: evaluates a project based on whether it will ensure ongoing
operations with the understanding that not executing the project will result
in operations being interrupted.
• Perform Quantitative Risk Analysis, Outputs.
Answer: Project documents updates
• Acquire Resources, Inputs (r).
Answer: Project Management Plan, Project documents, EEFs, OPAs (r)
• What is the format of a WBS?.
Answer: The format is typically done from the smallest digit up top down to
, the bottom it is separated into projects and tasks See image below
• Control Procurements, Inputs.
Answer: Project management plan Procurement documents Agreements
Approved change requests Work performance reports Work performance
data
• Monitor Communications, Outputs.
Answer: Work performance information, Change requests, Project
Management Plan updates, Project document updates
• Skinner's Theory.
Answer: Theory proposed that we learn language through association,
imitation and reinforcement
• Numeric project selection models.
Answer: Uses financial and other quantitative measures to drive decision
making (profit, and scoring models)
• Time value of money.
Answer: Money is worth more to an organization now than in the future. It
makes sense if you consider that if someone gave you $1,000 today and you
could invest the money such that the investment would return additional
value to you in the future
• A business strategy.
Answer: what a business plans on doing the short term and in the long term
• if age < 16:.
Answer: creates an if statement
• If a company wants to cancel a project right in the middle of a project what
does a PM do?.
Answer: Jumps to the closing phase immediately from whatever phase they
are at at the time
• After action report (AAR).
Answer: Another name for lessons learned review used by military
ACTUAL EXAM PAPER 2026 QUESTIONS
WITH ANSWERS GRADED A+
• title().
Answer: capitalizes first letter of each word
• Critical chain project management (CCPM).
Answer: Work each resource is expected to complete is checked to verify
that the resource will be capable and available when needed. Time buffers
are built into the schedule to handle situations when the critical resources
fall behind or aren't available
• Control Schedule, Tools & Techniques.
Answer: Data analysis, Critical path method, Project management
information system, Resource optimization, Leads and lags, Schedule
compression
• from csv import reader as scvreader.
Answer: mports individual function from a module and assigns it a new
name
• Operating Necessity.
Answer: evaluates a project based on whether it will ensure ongoing
operations with the understanding that not executing the project will result
in operations being interrupted.
• Perform Quantitative Risk Analysis, Outputs.
Answer: Project documents updates
• Acquire Resources, Inputs (r).
Answer: Project Management Plan, Project documents, EEFs, OPAs (r)
• What is the format of a WBS?.
Answer: The format is typically done from the smallest digit up top down to
, the bottom it is separated into projects and tasks See image below
• Control Procurements, Inputs.
Answer: Project management plan Procurement documents Agreements
Approved change requests Work performance reports Work performance
data
• Monitor Communications, Outputs.
Answer: Work performance information, Change requests, Project
Management Plan updates, Project document updates
• Skinner's Theory.
Answer: Theory proposed that we learn language through association,
imitation and reinforcement
• Numeric project selection models.
Answer: Uses financial and other quantitative measures to drive decision
making (profit, and scoring models)
• Time value of money.
Answer: Money is worth more to an organization now than in the future. It
makes sense if you consider that if someone gave you $1,000 today and you
could invest the money such that the investment would return additional
value to you in the future
• A business strategy.
Answer: what a business plans on doing the short term and in the long term
• if age < 16:.
Answer: creates an if statement
• If a company wants to cancel a project right in the middle of a project what
does a PM do?.
Answer: Jumps to the closing phase immediately from whatever phase they
are at at the time
• After action report (AAR).
Answer: Another name for lessons learned review used by military