Written by students who passed Immediately available after payment Read online or as PDF Wrong document? Swap it for free 4.6 TrustPilot
logo-home
Document preview thumbnail
Preview 1 out of 3 pages
Exam (elaborations)

CM 102 EXAM 2 QUESTIONS ANSWERED CORRECTLY LATEST UPDATE 2026

Document preview thumbnail
Preview 1 out of 3 pages

CM 102 EXAM 2 QUESTIONS ANSWERED CORRECTLY LATEST UPDATE 2026 What are the four steps in the design and bidding stage? - Answers Design, bid, award contract, notice to proceed What are the four steps of the construction process? - Answers Pre-construction, procurement, construction, post-construction What occurs during the design stage? - Answers Programming and feasibility, schematic design, design development, contract documents, code and compliance issues What occurs during the bidding stage? - Answers Plans and specifications are produced for bidders, coordinated by the architect to assist the owner in contract selection Who is a part of the onsite team? - Answers Project manager, general superintendent, assistant superintendent, field engineer Who is a part of the office team? - Answers Project manager, contract administrator, estimator What is due diligence? - Answers The process of identifying any problems or areas of concern What is the purpose of value engineering? - Answers To optimize resources to get the best value for the owner At what point does value engineering occur? - Answers Early on in the design-build process During what step of the construction process does permitting and inspection process preparation take place? - Answers Pre-construction stage What does "buying out" the job entail? - Answers During the procurement stage, labor, materials and subcontracts are purchased What two primary instruments are used to accomplish the procurement stage? - Answers Subcontracts and purchase orders What is mobilization? - Answers Setting up, laying out, and getting the job site safe and ready What are the four components of the post-construction stage? - Answers Project closeout, owner move in, warranty period, project evaluation During the project closeout, who performs the substantial completion? - Answers Architect During the project closeout, who performs the certificate of occupancy? - Answers Building inspector During the project closeout, who performs the final inspection? - Answers Building inspector What can happen after the completion of the punch list? - Answers Release of the final payment at the substantial completion What is an estimate? - Answers An educated guess What is a part of the cost estimate? - Answers Materials, labor, equipment and subcontracts What are conceptual estimates? - Answers No drawings to be based off of What are preliminary estimates? - Answers Preliminary set of drawings and dimensions What are detailed estimates? - Answers Complete set of plans and specs What are indirect costs? - Answers Overhead or general conditions (everything that isn't materials, labor, equipment or subcontracts) What is a work package? - Answers Detailed items of work bundled together under a particular trade Who approves submittals? - Answers The architect prior to installation What are submittals? - Answers Specific information, samples, mock ups, shop drawings Who prepares shop drawings? - Answers Vendor or subcontractor What is the purpose of creating an as-built drawing? - Answers To provide the owner with a set of drawings of what was actually installed and where it was placed What are the three components of the payment request? - Answers Schedule of values (established beginning of project), pay request continuation sheet (calculation of completed work, modified by change orders), and application for payment (occurs every billing cycle) What is retainage? - Answers Negative incentive to finish the job Stick approach (liquidated damages) - Answers Each day late guarantees payment from GC to owner What are change orders due to? - Answers Errors and omissions in the CD, change in scope by the owner What is a change order - Answers A written order by the architect or owner What are the four options of a dispute resolution? - Answers Full litigation (no one wins), arbitration, mini-trial, mediation What are the superintendents responsibilities? - Answers Organize the job site, set up the temporary field office, manage/control/coordinate (establish work hours) What are the four steps once material is ordered? - Answers Will-call and delivery, receipt and project site directions, inspection, acceptance or refusal What is a punch list? - Answers Detailed list that insures quality of all work items What is substantial completion? - Answers Punch list, architect inspection, end of project/beginning of warranty period, payments are released What is final completion? - Answers Final paperwork, release retainage What is the certificate of occupancy? - Answers Issued by building official, owner can move in What is included in the final document to the owner? - Answers Warranties, manuals, reports, as-builts What is a ROM estimate? - Answers No drawings What is a detailed estimate? - Answers Somewhat of an idea What are red flag items? - Answers Things that are unclear in the CDs How are general conditions typically calculated? - Answers It's the overhead What is partnering? - Answers Working together What are the steps of the billing cycle? - Answers Work completed, bills from subs, application for payment, payment received, pay subs What is a SWPPP? - Answers Storm water pollution prevention plan (big tarp thingies) Procedure used when including subcontractors and vendor bids? - Answers -soliciting the bids, (competitive bidding) -receiving the bids, -analyzing the bids, (any exclusions?) -and choosing the bids. (not always the lowest price General conditions - Answers Cost that occur during a project that don't involve swinging a hammer or installing something permanently in your home. ... They fall roughly into three categories: site management, material handling and project management Important factors related to subcontractor coordination and management? - Answers Resist bringing subs onto the job until 100% ready for them •Make sure subs have everything they need to proceed •Pay all subs promptly upon completion of their work Common items related to planning site logistics - Answers Pedestrian safety, employee parking, job site access, equipment, traffic control, etc... Company image and positive publicity on a job site? - Answers -Appearing as a good neighbor by keeping the jobsite clean, limiting noise, and controlling dust will keep the project from being slowed down by bad publicity. What are manageable factors of productivity? - Answers ANYTHING BUT SAFETY!!! -Crowded work spaces (labor, materials, debris) -Poor coordination of work activities »Incomplete or incorrect work from previous sub -Poor supervision or lack of supervision -Inexperienced of poorly trained workforce -Not having the proper tools and equipment -Adverse weather conditions

Content preview

CM 102 EXAM 2 QUESTIONS ANSWERED CORRECTLY LATEST UPDATE 2026

What are the four steps in the design and bidding stage? - Answers Design, bid, award contract,
notice to proceed
What are the four steps of the construction process? - Answers Pre-construction, procurement,
construction, post-construction
What occurs during the design stage? - Answers Programming and feasibility, schematic design,
design development, contract documents, code and compliance issues
What occurs during the bidding stage? - Answers Plans and specifications are produced for bidders,
coordinated by the architect to assist the owner in contract selection
Who is a part of the onsite team? - Answers Project manager, general superintendent, assistant
superintendent, field engineer
Who is a part of the office team? - Answers Project manager, contract administrator, estimator
What is due diligence? - Answers The process of identifying any problems or areas of concern
What is the purpose of value engineering? - Answers To optimize resources to get the best value for
the owner
At what point does value engineering occur? - Answers Early on in the design-build process
During what step of the construction process does permitting and inspection process preparation take
place? - Answers Pre-construction stage
What does "buying out" the job entail? - Answers During the procurement stage, labor, materials and
subcontracts are purchased
What two primary instruments are used to accomplish the procurement stage? - Answers
Subcontracts and purchase orders
What is mobilization? - Answers Setting up, laying out, and getting the job site safe and ready
What are the four components of the post-construction stage? - Answers Project closeout, owner
move in, warranty period, project evaluation
During the project closeout, who performs the substantial completion? - Answers Architect
During the project closeout, who performs the certificate of occupancy? - Answers Building inspector
During the project closeout, who performs the final inspection? - Answers Building inspector
What can happen after the completion of the punch list? - Answers Release of the final payment at
the substantial completion
What is an estimate? - Answers An educated guess
What is a part of the cost estimate? - Answers Materials, labor, equipment and subcontracts
What are conceptual estimates? - Answers No drawings to be based off of
What are preliminary estimates? - Answers Preliminary set of drawings and dimensions
What are detailed estimates? - Answers Complete set of plans and specs
What are indirect costs? - Answers Overhead or general conditions (everything that isn't materials,
labor, equipment or subcontracts)
What is a work package? - Answers Detailed items of work bundled together under a particular trade
Who approves submittals? - Answers The architect prior to installation
What are submittals? - Answers Specific information, samples, mock ups, shop drawings
Who prepares shop drawings? - Answers Vendor or subcontractor
What is the purpose of creating an as-built drawing? - Answers To provide the owner with a set of
drawings of what was actually installed and where it was placed
What are the three components of the payment request? - Answers Schedule of values (established
beginning of project), pay request continuation sheet (calculation of completed work, modified by
change orders), and application for payment (occurs every billing cycle)
What is retainage? - Answers Negative incentive to finish the job
Stick approach (liquidated damages) - Answers Each day late guarantees payment from GC to owner
What are change orders due to? - Answers Errors and omissions in the CD, change in scope by the
owner
What is a change order - Answers A written order by the architect or owner
What are the four options of a dispute resolution? - Answers Full litigation (no one wins), arbitration,
mini-trial, mediation
What are the superintendents responsibilities? - Answers Organize the job site, set up the temporary
field office, manage/control/coordinate (establish work hours)

Document information

Uploaded on
March 20, 2026
Number of pages
3
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers
$11.49

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
TutorJosh
3.4
(74)
Sold
481
Followers
16
Items
32589
Last sold
3 days ago



Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions