Written by students who passed Immediately available after payment Read online or as PDF Wrong document? Swap it for free 4.6 TrustPilot
logo-home
Exam (elaborations)

DBIA Exam 1 Actual Exam QUESTIONS AND ANSWERS 2026 | Design-Build Fundamentals Complete Q&A Graded A+ | Pass Guaranteed - A+ Graded

Rating
-
Sold
-
Pages
28
Grade
A+
Uploaded on
20-02-2026
Written in
2025/2026

DBIA Exam 1 Actual Exam QUESTIONS AND ANSWERS 2026 | Design-Build Fundamentals Complete Q&A Graded A+ | Pass Guaranteed - A+ Graded

Institution
DBIA
Course
DBIA

Content preview

DBIA Exam 1 Actual Exam QUESTIONS
AND ANSWERS 2026 | Design-Build
Fundamentals Complete Q&A Graded A+ |
Pass Guaranteed - A+ Graded

Questions 1-12

Question 1

What is the defining characteristic of the design-build project delivery method?

A. The owner holds separate contracts with designer and contractor

B. A single entity contracts with the owner to provide both design and construction services
[CORRECT]

C. The designer hires the contractor to build the project

D. The owner acts as the general contractor

Correct Answer: B

Rationale: Design-build is defined by a single point of responsibility—one entity (the design-
builder) contracts with the owner to deliver both design and construction services. This creates
unified accountability. Option A describes design-bid-build. Option C describes design-bid-build
with a construction manager. Option D describes owner-construction management.

Question 2

Compared to design-bid-build, design-build typically results in:

A. Longer project delivery time due to sequential phases

B. Reduced project delivery time through overlapping design and construction [CORRECT]

C. Higher frequency of change orders

D. Increased adversarial relationships between parties

Correct Answer: B

Rationale: Design-build enables "fast-tracking"—starting construction before design is
complete—reducing overall delivery time. Option A describes design-bid-build. Option C is

,incorrect; design-build typically has fewer change orders due to early collaboration. Option D is
opposite; design-build fosters collaboration.

Question 3

Which of the following is NOT a typical advantage of design-build?

A. Single point of responsibility

B. Enhanced collaboration and innovation

C. Guaranteed lowest initial price [CORRECT]

D. Reduced administrative burden on owner

Correct Answer: C

Rationale: Design-build offers many advantages but does not guarantee the lowest initial price.
Low-bid procurement may achieve lower initial prices but often with higher total costs due to
changes and disputes. Options A, B, and D are established design-build advantages.

Question 4

In the "bridging" procurement approach:

A. The owner hires a designer to develop preliminary design, then the design-builder completes
design and construction [CORRECT]

B. The design-builder bridges the gap between design and construction phases

C. The owner acts as the bridge between designer and builder

D. Financing bridges the funding gap

Correct Answer: A

Rationale: Bridging is a hybrid where the owner hires a designer (bridging consultant) to develop
preliminary design, performance criteria, and bridging documents, then procures a design-builder
to complete design and construct. This provides owner control over early design while retaining
design-build benefits.

Question 5

Design-build differs from Construction Manager at Risk (CMAR) primarily in that:

A. CMAR provides a single point of responsibility; design-build does not

B. Design-build provides a single point of responsibility for design and construction; CMAR
splits responsibility [CORRECT]

C. Both have identical risk allocation

, D. CMAR always uses lump sum pricing; design-build never does

Correct Answer: B

Rationale: In design-build, one entity holds both design and construction contracts with the
owner. In CMAR, the owner holds separate contracts with designer and CM, who then manages
construction trade contracts. The CM "at risk" guarantees a GMP but doesn't unify design and
construction responsibility like design-build.

Question 6

Which project delivery method most closely integrates design, construction, and operations
through shared risk/reward?

A. Design-bid-build

B. Design-build

C. Integrated Project Delivery (IPD) [CORRECT]

D. Public-private partnership (P3)

Correct Answer: C

Rationale: IPD is the most integrated, with owner, designer, and builder sharing risk/reward
through a multi-party agreement and collaborative decision-making. Design-build (B) has single-
point responsibility but not necessarily shared financial risk. P3 (D) focuses on
financing/operations, not necessarily integration.

Question 7

The "single point of responsibility" in design-build means:

A. Only one person works on the project

B. The owner has one entity accountable for both design and construction performance
[CORRECT]

C. The designer is solely responsible

D. The contractor is solely responsible

Correct Answer: B

Rationale: Single point of responsibility means the owner contracts with one entity (design-
builder) who is accountable for both design and construction, eliminating gaps in responsibility.
Options A, C, and D misinterpret the concept.

Question 8

Written for

Institution
DBIA
Course
DBIA

Document information

Uploaded on
February 20, 2026
Number of pages
28
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

$15.99
Get access to the full document:

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Get to know the seller
Seller avatar
EMPRESS254
1.0
(1)

Get to know the seller

Seller avatar
EMPRESS254 Chamberlain College Of Nursing
View profile
Follow You need to be logged in order to follow users or courses
Sold
6
Member since
6 months
Number of followers
0
Documents
646
Last sold
11 hours ago
Empress

One stop shop for all all study materials, Study guides,Exams and all assignments and homeworks.

1.0

1 reviews

5
0
4
0
3
0
2
0
1
1

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions