For hot work operation with citywide permit, the owner of the premises of the hot work
operation areas must be notified in writing by the citywide permit holder ______ the hot work
is to be started. - correct answer -at least 48 hours before
The pre-hot work check must be conducted by the responsible person before hot work is
authorized and __________ - correct answer -least once per day.
The check reports must be kept at the work site during the work, made available for inspection
by a representative of the FDNY, and maintained on the premises for a minimum of - correct
answer -48 hours after work is complete.
A pre-hot work check must be conducted at least - correct answer -once per day
Hot work operations involving cutting or welding shall be conducted at least - correct answer -
35 feet from combustible materials and combustible waste
All other hot work operations shall be conducted at least - correct answer -25 feet from
combustible materials and combustible waste
Sprinkler system protection ____________while hot work is performed. - correct answer -must
not be shut off or impaired
& ANSWERS WITH DETAILED RATIONALES | INSTANT
PDF DOWNLOAD
For hot work operation with citywide permit, the owner of the premises of the hot work
operation areas must be notified in writing by the citywide permit holder ______ the hot work
is to be started. - correct answer -at least 48 hours before
The pre-hot work check must be conducted by the responsible person before hot work is
authorized and __________ - correct answer -least once per day.
The check reports must be kept at the work site during the work, made available for inspection
by a representative of the FDNY, and maintained on the premises for a minimum of - correct
answer -48 hours after work is complete.
A pre-hot work check must be conducted at least - correct answer -once per day
Hot work operations involving cutting or welding shall be conducted at least - correct answer -
35 feet from combustible materials and combustible waste
All other hot work operations shall be conducted at least - correct answer -25 feet from
combustible materials and combustible waste
Sprinkler system protection ____________while hot work is performed. - correct answer -must