Module 1: COR Foundations & the Acquisition Lifecycle
1. What is the primary role of a Contracting Officer's Representative (COR)?
ANSWER ✓ To assist the Contracting Officer (CO) in the technical administration and
oversight of a contract, serving as the government's eyes and ears at the performance
site to ensure the contractor delivers what the government paid for.
2. A COR's authority is derived directly from the ___.
ANSWER ✓ Warrant held by the Contracting Officer, as delegated in the COR's Letter of
Appointment.
3. What is the single most important document for a COR?
ANSWER ✓ The COR Letter of Appointment, which defines the specific limits of their
authority and responsibilities.
4. What is a COR expressly FORBIDDEN from doing?
ANSWER ✓ Making any commitments to, or issuing any directions to, the contractor
that would change the contract's price, terms, conditions, or scope (PTS).
5. Which phase of the Acquisition Lifecycle involves developing requirements and
the Acquisition Strategy?
ANSWER ✓ The Planning Phase (Material Solution Analysis and Technology Maturation
& Risk Reduction phases in DoD parlance).
6. During which phase does the COR role become most active?
ANSWER ✓ The Sustaining Phase (Operations & Support), which includes contract
administration, surveillance, and acceptance.
7. The COR is a key participant in which part of the Requirements Definition
process?
, ANSWER ✓ Developing the Statement of Work (SOW) or Performance Work Statement
(PWS), ensuring it is clear, measurable, and achievable.
8. What is the purpose of an Acquisition Plan?
ANSWER ✓ To document the overall strategy for managing an acquisition, including
the acquisition approach, competition strategy, and source selection procedures.
9. What document formally establishes the need for a service or supply?
ANSWER ✓ The Requirement Document (e.g., Statement of Need, Initial Capabilities
Document (ICD), or approved Requirement in a financial system).
10. True or False: A COR can be appointed after contract award.
ANSWER ✓ True. While ideal to involve the COR earlier, appointments are often made
post-award. The COR must review all pre-award documentation to understand the
contract's intent.
Module 2: Understanding the Contract
11. What are the three overarching types of contracts?
ANSWER ✓ Fixed-Price, Cost-Reimbursement, and Time-and-Materials/Labor-Hour.
12. What type of contract places maximum risk on the contractor and minimum
risk on the government?
ANSWER ✓ Firm-Fixed-Price (FFP) contract.
13. What type of contract places maximum risk on the government and should
only be used when requirements are not well-defined?
ANSWER ✓ Cost-Reimbursement contracts (e.g., CPFF, CPIF).
14. When is a Time-and-Materials (T&M) contract appropriate?
ANSWER ✓ Only when it is not possible to accurately estimate the extent or duration of
the work or to anticipate costs with any reasonable degree of confidence, and it includes
proper oversight and ceiling price controls.
15. What is the fundamental difference between a Statement of Work (SOW) and a
Performance Work Statement (PWS)?
, ANSWER ✓ A SOW specifies how the work is to be done (methods). A PWS
specifies what is to be accomplished (results/outcomes), giving the contractor more
flexibility in approach.
16. What section of the contract contains the mandatory clauses and provisions
that govern the legal relationship?
ANSWER ✓ The Contract Clauses (FAR/DFARS provisions) section.
17. What is the purpose of the Quality Assurance Surveillance Plan (QASP)?
ANSWER ✓ It is the COR's primary surveillance tool, outlining how the government will
monitor and evaluate contractor performance against the standards in the PWS/SOW.
18. What is the difference between "Inspection" and "Acceptance"?
ANSWER ✓ Inspection is the process of examining the supplies or services. Acceptance
is the formal act of the government assuming ownership or approving services, which
can only be done by the Contracting Officer or their duly authorized representative
(often the COR, if delegated).
19. Where are the specific, measurable standards for performance found?
ANSWER ✓ In the Performance Requirements Summary (PRS) or the Quality Assurance
Surveillance Plan (QASP), which is tied to the PWS/SOW.
20. What contract document specifies the items, quantities, and prices to be paid?
ANSWER ✓ The Contract Line Item Number (CLIN) and Sub-LIN structure, detailed in
the Price/Cost Schedule (e.g., Section B of the SF-33).
Module 3: COR Responsibilities & Ethics
21. What are the "Three Cs" of COR responsibilities?
ANSWER ✓ Compliance, Communication, and Documentation.
22. A contractor representative offers you tickets to a major sporting event. What
should you do?
ANSWER ✓ Politely and firmly decline the gift, report the offer to your supervisor and
the Contracting Officer, and document the interaction. This is a potential violation of the
Procurement Integrity Act.